STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: May 27, 2020
COUNCIL DISTRICT(S): 6
DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with Atkins Bros. Equipment Co., Inc. for the installation of a 30-inch diameter wastewater pipeline in Goodnight Lane from Southwell Road to Joe Field Road - Not to exceed $1,942,005.00, from $8,481,325.00 to $10,423,330.00 - Financing: Wastewater Capital Improvement E Fund
Body
BACKGROUND
On August 24, 2016, City Council authorized a contract for the installation of water and wastewater mains at 14 locations to Atkins Bros. Equipment Co., Inc. by Resolution No. 16-1135. This action will authorize Change Order No. 1 to the construction services contract with Atkins Bros. Equipment Co., Inc. for the installation of a 30-inch diameter wastewater main by tunneling rather than conventional open cut trenching.
During construction in Goodnight Lane, unforeseen subsurface conditions related to soil instability were encountered. The contractor attempted to employ conventional measures to maintain trench safety and lateral soil stability in order to protect adjacent paving and property, and maintain access to adjacent businesses. Despite all conventional attempts, the contractor was not able to continue trenching without unacceptable safety risks, property damage, and business access limitations. The contractor has provided an acceptable proposal to change from open cut trenching to tunneling, which allowed the 30-inch pipeline to be installed and afforded more protection to adjacent property and infrastructure as well as improved access to adjacent businesses.
Approval of this item will allow completion of this construction contract. The project improves the existing wastewater collection system and provides adequate capacity for future development in the project area.
ESTIMATED SCHEDULE OF PROJECT
Begin Construction June 2020
Complete Construction August 2021
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On August 24, 2016, City Council authorized a contract with Atkins Bros. Equipment Co., Inc. for the installation of water and wastewater mains at 14 locations by Resolution No. 16-1135.
FISCAL INFORMATION
Fund |
FY 2020 |
FY 2021 |
Future Years |
Wastewater Capital Improvement E Fund |
$1,942,005.00 |
$0.00 |
$0.00 |
Construction $ 8,481,325.00
Change Order No. 1 (this action) $ 1,942,005.00
Total Project Cost $10,423,330.00
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Category |
M/WBE Goal |
M/WBE % |
M/WBE $ |
$1,942,005.00 |
Construction |
25.00% |
14.93% |
$290,000.00 |
• This contract does not meet the M/WBE goal, but complies with good faith efforts. |
• Change Order No. 1 - 23.87% Overall MWBE Participation |
• Atkins Bros. Equipment Co., Inc. - Non-local |
OWNER
Atkins Bros. Equipment Co., Inc.
Mike Atkins, Chief Executive Officer
MAP
Attached