Dallas Logo
File #: 20-1344    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/16/2020 In control: Water Utilities Department
On agenda: 9/9/2020 Final action: 9/9/2020
Title: Authorize Supplemental Agreement No. 1 to the professional services contract with Signature Automation, LLC for additional engineering services related to the design, construction administration, and start-up associated with Supervisory Control and Data Acquisition improvements at the Southside Wastewater Treatment Plant - Not to exceed $2,630,000.00, from $2,680,000.00 to $5,310,000.00 - Financing: Wastewater Capital Improvement D Fund
Indexes: 8
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 9, 2020
COUNCIL DISTRICT(S):|910|DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 1 to the professional services contract with Signature Automation, LLC for additional engineering services related to the design, construction administration, and start-up associated with Supervisory Control and Data Acquisition improvements at the Southside Wastewater Treatment Plant - Not to exceed $2,630,000.00, from $2,680,000.00 to $5,310,000.00 - Financing: Wastewater Capital Improvement D Fund

Body
BACKGROUND

The City of Dallas owns and operates two wastewater treatment plants with a combined treatment capacity of 280 million gallons per day. Southside Wastewater Treatment Plant (SWWTP) is located in southeast Dallas and is permitted to treat an average annual flow of 110 million gallons of wastewater per day. The existing Supervisory Control and Data Acquisition (SCADA) system at the SWWTP is reaching the end of its useful life. All hardware and software are obsolete and currently not supported by the original manufacturers.

On May 22, 2019, City Council authorized a professional services contract with Signature Automation, LLC for services related to the design and construction of SCADA improvements at the SWWTP. The project includes the evaluation and design of instrumentation and control equipment to optimize treatment operations by improving reliability, consistency and minimizing treatment cost. As part of the original scope of the contract, Signature Automation, LLC has determined the instrumentation and equipment needs to improve automation and control of the treatment processes at the plant.

This action will authorize Supplemental Agreement No. 1 with Signature Automation, LLC for configuration and programming efforts of the...