Dallas Logo
File #: 20-1426    Version: 1 Name:
Type: CONSENT AGENDA Status: Deferred
File created: 7/27/2020 In control: Department of Planning and Urban Design
On agenda: 9/23/2020 Final action: 9/23/2020
Title: Authorize (1) a Project Specific Agreement with Dallas County for the Transit-Oriented Development Planning and Implementation Project Major Capital Improvement Program (MCIP) 10227 and MCIP 40221; (2) the receipt and deposit of funds in an amount not to exceed $234,000.00 in the Capital Projects Reimbursement Fund; and (3) the establishment of appropriations in an amount not to exceed $234,000.00 in the Capital Projects Reimbursement Fund - Not to exceed $234,000.00 - Financing: Capital Projects Reimbursement Fund
Indexes: 100
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Economic and Neighborhood Vitality

AGENDA DATE:                     September 23, 2020

COUNCIL DISTRICT(S):                     All

DEPARTMENT:                     Department of Planning and Urban Design

EXECUTIVE:                     Dr. Eric A. Johnson

______________________________________________________________________

SUBJECT

 

title

Authorize (1) a Project Specific Agreement with Dallas County for the Transit-Oriented Development  Planning and Implementation Project Major Capital Improvement Program (MCIP) 10227 and MCIP 40221; (2) the receipt and deposit of funds in an amount not to exceed $234,000.00 in the Capital Projects Reimbursement Fund; and (3) the establishment of appropriations in an amount not to exceed $234,000.00 in the Capital Projects Reimbursement Fund - Not to exceed $234,000.00 - Financing: Capital Projects Reimbursement Fund

 

body

BACKGROUND

 

Through the fiscal year 19-20 budget adoption, the City of Dallas has committed to updating the forwardDallas! Comprehensive Land Use Plan and is anticipated to launch this project in September 2020.  Consultant costs for the project will be $649,960.00 to be funded through the Building Inspection Enterprise Fund and Dallas County MCIP. The project scope will include a focus on Transit-Oriented Development (TOD) Planning and Implementation. The Dallas County MCIP authorized by Court Order 2011-1287 dated August 2, 2011, approved specified projects including City of Dallas TOD Planning and Implementation Project MCIP 10227 and MCIP 40221 in the City of Dallas with a funding allocation of $234,000.00.

 

This action will authorize execution of a Project Specific Agreement with Dallas County, receipt and deposit of $234,000.00 from Dallas County and appropriation in the same amount in the Capital Projects Reimbursement Fund.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Project                                                                                    September 2020

Draft Plan                                                                     September 2021

Council action on Plan                                          February 2022

 

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2020-21

FY 2021-22

Future Years

Capital Projects Reimbursement Fund

$234,000.00

$0.00

$0.00

 