File #: 20-1471    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/31/2020 In control: Department of Public Works
On agenda: 9/23/2020 Final action: 9/23/2020
Title: Authorize a construction contract for the construction of Street Reconstruction Group 17-1408 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of ten - Not to exceed $2,201,310.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($1,848,230.00), Water Utilities Capital Improvement D Fund ($174,700.00), Water Utilities Capital Construction Fund ($9,700.00), Wastewater Utilities Capital Improvement E Fund ($159,780.00), and Wastewater Utilities Capital Construction Fund ($8,900.00)
Indexes: 14
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 23, 2020
COUNCIL DISTRICT(S): 14
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a construction contract for the construction of Street Reconstruction Group 17-1408 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of ten - Not to exceed $2,201,310.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($1,848,230.00), Water Utilities Capital Improvement D Fund ($174,700.00), Water Utilities Capital Construction Fund ($9,700.00), Wastewater Utilities Capital Improvement E Fund ($159,780.00), and Wastewater Utilities Capital Construction Fund ($8,900.00)

Body
BACKGROUND

Estrada Concrete Company, LLC is a Dallas-based corporation, operating within the corporate city limits of Dallas, Texas.

This action will authorize a construction contract with Estrada Concrete Company, LLC for the construction of three street reconstruction projects as Street Reconstruction Group 17-1408.

The project scope will include replacing the existing deteriorating streets with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, pavement markings, drainage system, traffic signal, and water and wastewater improvements.

Following are the locations and construction costs for each project:

Project Council District Amount

Maple Avenue from McKinney Avenue
to Mahon Street 14 $849,466.04

Maple Avenue from Mahon Street
to Cedar Springs Road 14 $496,910.84

Maple Avenue from Randall Street
to Wolf Street 14 $854,933.12

The following chart illustrates Estrada Concrete Company, LLC's contractual activities with the City of Dallas for the past three years:

PBW DWU PKR

Projects Completed 0 0 0
Active Projects 6 ...