Title: Authorize (1) Supplemental Agreement No. 1 to increase the architectural services contract with Harrison Kornberg Architects for additional design services and construction administration for the Meyerson Symphony Center located at 2301 Flora Street; (2) the receipt and deposit of additional funds in an amount not to exceed $40,370.00 from the Dallas Symphony Association, Inc. for additional architectural, and engineering design, and construction administration services for the Meyerson Symphony Center and (3) an increase in appropriations in an amount of $40,370.00 in the Gifts and Donations Fund - Not to exceed $40,370.00, from $695,222.00 to $735,592.00 - Financing: Gifts and Donations Fund ($40,370.00) and Estimated Revenue: Gifts and Donations Fund ($40,370.00)
Indexes: 14
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     October 28, 2020

COUNCIL DISTRICT(S):                     14

DEPARTMENT:                     Office of Bond and Construction Management

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize (1) Supplemental Agreement No. 1 to increase the architectural services contract with Harrison Kornberg Architects for additional design services and construction administration for the Meyerson Symphony Center located at 2301 Flora Street; (2) the receipt and deposit of additional funds in an amount not to exceed $40,370.00 from the Dallas Symphony Association, Inc. for additional architectural, and engineering design, and construction administration services for the Meyerson Symphony Center and (3) an increase in appropriations in an amount of $40,370.00 in the Gifts and Donations Fund - Not to exceed $40,370.00, from $695,222.00 to $735,592.00 - Financing: Gifts and Donations Fund ($40,370.00) and Estimated Revenue: Gifts and Donations Fund ($40,370.00)

 

Title

Body

BACKGROUND

 

This action will authorize the receipt and deposit of a private donation from the Dallas Symphony Association, Inc. to increase the architectural services contract with Harrison-Kornberg Architects, LLC, for additional design services for roofing renovations at the Meyerson Symphony Center, a project approved by the citizens of Dallas in the 2017 Bond Program. Dallas Symphony Association, Inc. is contributing $40,370.00 towards the architectural, and engineering design, and construction administration services.

 

This action will also authorize Supplemental No. 1 to increase the architectural services contract with Harrison-Kornberg Architects, LLC for additional design services and construction administration at Meyerson Symphony Center located at 2301 Flora Street.

 

Deferral of this item would delay design solution for additional roofing repairs located in the facility.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Design                                           November 2020

Complete Design                                           December 2020

Begin Construction                                           January 2021

Complete Construction                     August 2021

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On February 13, 2019, City Council authorized an Architectural services contract with Harrison Kornberg Architects, LLC for architectural and engineering design and construction administration services for the Meyerson Symphony Center Improvements, located at 2301 Flora Street by Resolution 19-0249.

 

FISCAL INFORMATION

 

Estimated Revenue: Gifts and Donations Fund $40,370.00

 

Fund

FY 2021

FY 2022

Future Years

Gifts and Donations Fund

$40,370.00

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$40,370.00

Construction

25.00%

9.09%

$3,670.00

Business Inclusion and Development does not apply to item under $50,000.00 however the prime is certified MWBE

Supplemental Agreement No. 1 - 65.73% Overall M/WBE participation

Harrison Kornberg Architects - Non-Local; Workforce - 14.70% Local

 