Dallas Logo
File #: 20-2020    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved as an Individual Item
File created: 10/9/2020 In control: Park & Recreation Department
On agenda: 11/11/2020 Final action: 11/11/2020
Title: Authorize a construction contract for the construction of a playground and sidewalk extension at Lindsley Park located at 7100 Lindsley Avenue - C. Green Scaping, lowest responsible bidder of six - Not to exceed $363,389.76 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Funds) ($329,564.76) and Equity Revitalization Capital Fund ($33,825.00)
Indexes: 14
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life
AGENDA DATE: November 11, 2020
COUNCIL DISTRICT(S): 14
DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT

Title
Authorize a construction contract for the construction of a playground and sidewalk extension at Lindsley Park located at 7100 Lindsley Avenue - C. Green Scaping, lowest responsible bidder of six - Not to exceed $363,389.76 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Funds) ($329,564.76) and Equity Revitalization Capital Fund ($33,825.00)

Body
BACKGROUND

On July 29, 2020, the City of Dallas advertised for bids for the construction of a playground and sidewalk extension at Lindsley Park located at 7100 Lindsley Avenue. In response to the advertisement, the Office of Procurement Services received bids from six firms on August 21, 2020.

This action will award a construction contract to C. Green Scaping for the construction of a playground and sidewalk extension at Lindsley Park. This project was included in the 2017 Bond Program.

The scope of work includes replacement of the playground equipment, surfacing and sub-drainage, the extension of a sidewalk from Shadyside Lane to Lindsley Drive, the replacement of the existing basketball court goals, storm drainage system improvements and Americans with Disabilities Act accessible curb ramps and poured-in-place resilient surfacing for the two to five age group. Equity Revitalization Capital Funds, in an amount not to exceed $33,825.00 will be utilized to fund the poured-in-place surfacing.

The following chart illustrates C. Green Scaping's contractual activities with the City of Dallas for the past three years:

PBW DWU PKR

Projects Completed|999||910|Active Projects|999||910|Change Orders |999||910|Projects Requiring Liquidated Damages|99||99||910|Projects Completed by Bonding Company|999||910|
ESTIMATED SCHEDULE OF P...

Click here for full text