Dallas Logo
File #: 20-2040    Version: 1 Name:
Type: ITEMS FOR INDIVIDUAL CONSIDERATION Status: Approved
File created: 10/12/2020 In control: Water Utilities Department
On agenda: 11/11/2020 Final action: 11/11/2020
Title: Authorize the second step of acquisition for condemnation by eminent domain to acquire an improved tract of land containing approximately 11.755 acres, from Daniel Ghebreyohannes and Candace Capital, LLC, located on Sargent Road near its intersection with Morrell Avenue for the Dallas Floodway Extension Project - Not to exceed $1,510.00 ($10.00, plus closing costs and title expenses not to exceed $1,500.00) - Financing: Trinity R. Corridor 04-05 Fund (1998 General Obligation Bond Funds)
Indexes: 4
Attachments: 1. Map, 2. Resolution, 3. Exhibit A
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: November 11, 2020
COUNCIL DISTRICT(S):|910|DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

title
Authorize the second step of acquisition for condemnation by eminent domain to acquire an improved tract of land containing approximately 11.755 acres, from Daniel Ghebreyohannes and Candace Capital, LLC, located on Sargent Road near its intersection with Morrell Avenue for the Dallas Floodway Extension Project - Not to exceed $1,510.00 ($10.00, plus closing costs and title expenses not to exceed $1,500.00) - Financing: Trinity R. Corridor 04-05 Fund (1998 General Obligation Bond Funds)

body
BACKGROUND

The City of Dallas is the owner and operator of the Dallas Levee System extending from the Elm and West Forks of the Trinity River through the main stem and terminating at Interstate Highway 20. This system is regulated by the U.S. Army Corps of Engineers (USACE). In addition to regulating the Dallas Levee System, the USACE and City have been cost participating in two separate federal projects to improve the public safety of the residents and businesses that are served by this system. The City is required to own, in fee simple, all parcels related to the Dallas Levee System.

In July 2018, the Dallas Levee System flood risk management projects included in the Modified Dallas Floodway Project (DF) and the Dallas Floodway Extension (DFE) were authorized for funding under the Supplemental Appropriation in the Bipartisan Budget Act of 2018- Public Law 115-123 (PL- 115-123). This information has been presented to the City Council and provided in memorandum to the City Council at major milestones since the notification by the USACE. All work associated with the design and construction of these improvements is being performed by USACE with the City serving as a technical advisor and client....

Click here for full text