File #: 20-2216    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 11/2/2020 In control: Department of Convention and Event Services
On agenda: 1/13/2021 Final action:
Title: Authorize a construction services contract for construction of the elevator and escalator modernization at the Kay Baily Hutchison Convention Center Dallas, located at 650 South Griffin Street - Sawyers Construction, Inc., best value proposer of two - Not to exceed $6,498,768.00 - Financing: Convention Center Construction Fund
Indexes: 2
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life

AGENDA DATE:                     January 13, 2021

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Convention and Event Services

EXECUTIVE:                     Joey Zapata

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for construction of the elevator and escalator modernization at the Kay Baily Hutchison Convention Center Dallas, located at 650 South Griffin Street - Sawyers Construction, Inc., best value proposer of two - Not to exceed $6,498,768.00 - Financing: Convention Center Construction Fund

 

Body

BACKGROUND

 

On January 8, 2020, a Request for Competitive Sealed Proposals (RFCSP) was issued based on recommendations included in the AECOM Technical Services, Inc. evaluation and assessment report from September 3, 2018.  Two competitive sealed proposals were received on February 28, 2020, and proposals were evaluated by a Selection Committee following City procurement guidelines. Following review of the proposals and interviews with each contractor, the Selection Committee determined a final ranking of the proposals. The Committee’s unanimous recommendation as the best value proposer was Sawyers Construction, Inc.

The proposals were evaluated and ranked according to the published criteria in the project specifications, as outlined below:

Criteria                                                                                                                                                                                             Points

 

Proposed Construction Cost                                                                                                                                 40

Schedule                                                                                                                                                                                                  5

Experience/References                                                                                                                                                     30

Project Team                                                                                                                                                                             5

Financial Sufficiency                                                                                                                                                       5

Business Inclusion and Development Requirements                                                                  15

 

                                                                                                                                                                                             Total                     100

 

 

 

This action will authorize a construction services contract with Sawyers Construction, Inc. to provide construction services for the Kay Bailey Hutchison Convention Center Dallas (KBHCCD) elevator and escalator modernization as recommended by AECOM Technical Services, Inc. in their evaluation and assessment report included in the construction documents.

The KBHCCD dates to 1957 when the Dallas Memorial Auditorium first opened for events. Since then the KBHCCD completed major expansions to the facility in 1974, 1984, 1994, and 2002 that included exhibition spaces, meeting rooms, ballrooms, and service areas. The Center is dependent on its vertical transportation system of elevators and escalators to move people, equipment, food services, and freight from floor to floor in support of events and daily operations.  The AECOM vertical transportation assessment report recommended modernization to 5 elevators and 12 escalators at the facility.  The equipment identified for modernization has either exceeded its useful life and is recommended for modernization to improve efficiency, reduce maintenance, and update safety features to the current code or is included as part of a facility renovation to remove equipment not in use that is a hazard if it remains.

 

The AECOM report set a useful life for the existing KBHCCD vertical transportation equipment of 30 years.  The equipment recommended for modernization is as follows:

 

Equipment Name

Date of Install

Estimated End of Useful Life (EUL)

Years Over EUL

Escalator 1, 2, 3, 4, 5, 6, 7, 8, 9, 10

1972

2002

+18 years

Escalator 23, 24

1990

2020

0

Elevator 1 (Passenger Service)

1957

1987

+33 years

Elevator 2 (Freight))

1972

2002

+18 years

Elevator 3 (Passenger)

1972

2002

+18 years

Elevator 6, 8 (Freight)

1981

2011

+9 years

 

The equipment has been maintained in serviceable condition by the KBHCCD’s contracted maintenance company and has remained certified by the State.  However, the equipment’s down time due to part failure and age continues to increase, resulting in a negative impact on event attendee experiences and daily operational use.  In addition, the cost for replacement parts and contractor repair visits has become prohibitive, and existing equipment does not incorporate the most current safety features.

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                           December 2017

Completed Design                                           November 2019

Begin Construction                                           January 2021

Complete Construction                     December 2022

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On October 11, 2017, City Council authorized a professional services contract with AECOM Technical Services, Inc. by Resolution No. 17-1727.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Convention Center Construction Fund

$3,485,523.00

$2,094,763.00

$918,482.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Plan adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$6,498,768.00

Construction

25.00%

0.92%

$60,100.00

This contract does not meet the M/WBE goal, but complies with good faith efforts.

Sawyers Construction, Inc. - Dallas County; Workforce - 25.00% Local

 

PROCUREMENT INFORMATION

 

The following two proposals were received and opened on February 28, 2020:

 

*Denotes successful proposer

 

Proposers                                                                                    Base Bid                                               Ranking

 

*Sawyers Construction, Inc                     $6,498,768.00                                          1

 2307 Oak Lane, Suite 210

 Grand Prairie, Texas 75051

Diesel Design Build, LLC                                          $4,058,842.00                                          2

 

OWNER

 

Sawyers Construction, Inc.

 

Randy Sawyers, President