STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: January 13, 2021
COUNCIL DISTRICT(S): 13
DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with SYB Construction Company, Inc. for drainage improvements at the intersection of Douglas Avenue and Joyce Way - Not to exceed $61,677.00, from $4,293,456.25 to $4,355,133.25 - Financing: Storm Drainage Management Capital Construction Fund
Body
BACKGROUND
On January 22, 2020, City Council authorized a construction services contract with SYB Construction Company, Inc. for the installation of water and wastewater mains at six locations by Resolution No. 20-0221. After award of the contract, storm drainage concerns were identified at the intersection of Douglas Avenue and Joyce Way. Upon field investigation and coordination, it was determined that storm drainage improvements were warranted, and it was deemed most efficient to include the additional work as a part of this construction contract that includes water and wastewater main improvements in Douglas Avenue and Joyce Way.
This action will authorize Change Order No. 1 to the construction services contract with SYB Construction Company, Inc. for storm drainage improvements at the intersection of Douglas Avenue and Joyce Way. The additional work will not increase the contract duration and will provide for better drainage at this intersection.
ESTIMATED SCHEDULE OF PROJECT
Began Construction March 2020
Complete Construction September 2021
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On January 22, 2020, City Council authorized a construction services contract with SYB Construction Company, Inc. for the installation of water and wastewater mains at 6 locations by Resolution No. 20-0221.
FISCAL INFORMATION
Fund
FY 2020
FY 2021
Future Years
Storm Drainage Manageme...
Click here for full text