Dallas Logo
File #: 20-2292    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 11/9/2020 In control: Department of Aviation
On agenda: 1/13/2021 Final action:
Title: Authorize a construction services contract to provide construction services for the Dallas Love Field Entry Road Enhancements Project - The Fain Group, lowest responsible bidder of five - Not to exceed $13,060,705.28 - Financing: Aviation Construction Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     January 13, 2021

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Aviation

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract to provide construction services for the Dallas Love Field Entry Road Enhancements Project - The Fain Group, lowest responsible bidder of five - Not to exceed $13,060,705.28 - Financing: Aviation Construction Fund

 

Body

BACKGROUND

 

The 2015 Dallas Love Field, Airport Master Plan Update adopted by City Council identified several strategic development programs for safe, efficient, economically vibrant and responsive operations of the airport. The Dallas Love Field Entry Road Enhancements Project is one of several projects undertaken in response to the recommendations in the Airport Master Plan Update.

 

The project will install wider sidewalks; signature street and pedestrian lights; enhanced landscape and streetscape elements; a major public art sculpture as a placemaking symbol of the airport; high visibility crosswalks; guide signs; new airport entry signage; related safety and quality of life improvements. This project will improve pedestrian safety and upgrade aesthetics of the streetscape experience for pedestrians and vehicular passengers on Herb Kelleher Way from Mockingbird Lane to and around the airport terminal.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                     May 2018

Completed Design                     March 2020

Begin Construction                     February 2021

Complete Construction                     May 2022

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On April 11, 2018, City Council authorized a professional services contract with Freese and Nichols, Inc. for design and engineering services for improvements to the Dallas Love Field Entry Road Enhancements Project by Resolution No. 18-0517.

 

On February 12, 2020, City Council authorized Supplemental Agreement No. 1 to the professional services contract with Freese and Nichols, Inc. for additional services including electrical re-design, entry signage design, public art installation coordination, increased project management, project and bid phasing services, additional construction management and traffic signal modifications at pedestrian crossings for the Dallas Love Field Entry Road Enhancements Project by Resolution No. 20-0259.

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Aviation Construction Fund

$13,060,705.28

$0.00

$0.00

 

Original Design Contract                                                                                    $  1,095,000.00

Supplemental Agreement No. 1                                                               $     331,400.00

Construction (this action)                                                                                    $13,060,705.28

 

Total Project Cost                                                                                                         $14,487,105.28

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Plan adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$13,060,705.28

Construction

25.00%*

24.68%

$3,223,604.00

*This item reflects previous Business Inclusion and Development Policy M/WBE goal.

This contract does not meet the M/WBE goal, but complies with good faith efforts.

The Fain Group - Non Local; Workforce - 25.00% Local

 

PROCUREMENT INFORMATION

 

The following five bids were received and opened on October 9, 2020:

 

*Denotes successful bidder

 

Bidders                     Amount

 

*The Fain Group                     $13,060,705.28

 1616 North Sylvania Avenue

 Fort Worth, Texas 76111

Phillip May Corporation                     $13,741,446.30

Fort Worth Civil Constructors, LLC                     $14,099,050.91

Reyes Group                     $14,386,908.00

Ragel Group                     $15,852,664.99

 

Note: The City has received a protest regarding this procurement which has been addressed.  Please find attached the vendor protest letter and the City’s response.

 

OWNER

 

The Fain Group

 

Larry Frazier, President

 

MAP

 

Attached