Dallas Logo
File #: 20-1801    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 9/14/2020 In control: Department of Aviation
On agenda: 1/27/2021 Final action:
Title: Authorize the execution of a discretionary service agreement with Oncor Electric Delivery to relocate and install one single phase transformer and approximately 221 feet of duct bank in order to facilitate the Runway 13R/31L reconstruction project at Dallas Love Field in accordance with Federal Aviation Administration guidelines - Not to exceed $655,086.42 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     January 27, 2021

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Aviation

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

title

Authorize the execution of a discretionary service agreement with Oncor Electric Delivery to relocate and install one single phase transformer and approximately 221 feet of duct bank in order to facilitate the Runway 13R/31L reconstruction project at Dallas Love Field in accordance with Federal Aviation Administration guidelines - Not to exceed $655,086.42 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund

 

body

BACKGROUND

 

The Department of Aviation in accordance with the Federal Aviation Administration specifications and guidelines will award a construction contract for the Reconstruction of Runway 13R/31L at Dallas Love Field. The surface of the runway must be reconstructed to meet federal guidelines and provide safety for airport operations. Prior to commencement of the project, the City and Oncor have agreed to relocate and install one single phase transformer and approximately 221 feet of duct bank located within the Runway Object Free Area.

 

The Runway 13R/31L was originally constructed in 1965 and serves as one of the primary runways for commercial and general aviation takeoffs and landings at Dallas Love Field.  The runway was last rehabilitated in 1990.  The scope includes but is not limited to demolition, removal, reconstruction, realignment, and relocation of utilities such as Oncor Electric Delivery utilities to support the reconstruction project.

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

 

 

 

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Aviation Passenger Facility Charge - Near Term Projects Fund

$655,086.42

$0.00

$0.00

 

 