File #: 20-2349    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 11/23/2020 In control: Department of Public Works
On agenda: 1/27/2021 Final action:
Title: Authorize an Advance Funding Agreement with the Texas Department of Transportation (TxDOT) (CSJ No. 0918-47-237) for payment to TxDOT for engineering review and construction oversight cost for the design of a new roadway on Wheatland Road from the city limits to University Hills Boulevard in the amount of $8,500.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)
Indexes: 8
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     January 27, 2021

COUNCIL DISTRICT(S):                     8

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize an Advance Funding Agreement with the Texas Department of Transportation (TxDOT) (CSJ No. 0918-47-237) for payment to TxDOT for engineering review and construction oversight cost for the design of a new roadway on Wheatland Road from the city limits to University Hills Boulevard in the amount of $8,500.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

 

Body

BACKGROUND

 

This project is a partnership project between the City of Dallas.  The City is the lead agency responsible for administering design and construction of the project. This paving project will include construction of a new four-lane undivided roadway with reinforced concrete pavement, curb, gutter, bicycle/pedestrian facilities, intersection reconstruction, water, storm drainage, a new bridge, culvert and street lighting.

This action will authorize an Advance Funding Agreement (AFA) for the payment to TxDOT for the City’s share of the engineering design review costs associated with this project.  The estimated total project cost, including construction and the state's direct/indirect cost is $4,440,179.00, of which $3,400,000.00 is to be federally funded, $190,179.00 is to be funded by TxDOT, and the remaining $850,000.00 is to be funded by the City of Dallas 2017 Bond Program. The City will be responsible for any project cost overruns, in excess of the federal and state funding participation, as described in the agreement.

If the AFA is not approved at this time, it would delay the implementation of Wheatland Road from the city limits to University Hills Boulevard, thus delaying implementation of the 2017 Bond Program and other Dallas Water Utilities’ projects in the area and jeopardize the federal funding that has been allocated.  Without the federal funding, it will be unfeasible for the City to proceed with this project.

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Study                                                               April 2019

Completed Study                                          June 2020

Began Final Design                                          December 2020

Complete Final Design                     December 2021

Begin Construction                                          March 2022

Complete Construction                     September 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

 FY 2021

  FY 2022

Future Years

Street and Transportation Fund (2017 General Obligation Bond Fund)

$8,500.00

      $0.00

           $0.00

 

MAP

 

Attached