File #: 20-2508    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 12/17/2020 In control: Park & Recreation Department
On agenda: 1/27/2021 Final action:
Title: Authorize an increase in the construction services contract with Azteca Enterprises, Inc. for additional scope of work for construction for upgrades to the fire alarm, electrical distribution panels, heating, ventilation, and air conditioning controls systems, air treatment, and other miscellaneous work for the Fair Park Coliseum Facility Improvements Project located at 1438 Coliseum Drive - Not to exceed $851,357.27, from $10,138,840.87 to $?10,990,198.14? - Financing: Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund) ??????????
Indexes: 7
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life

AGENDA DATE:                     January 27, 2021

COUNCIL DISTRICT(S):                     7

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     John D. Jenkins

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Azteca Enterprises, Inc. for additional scope of work for construction for upgrades to the fire alarm, electrical distribution panels, heating, ventilation, and air conditioning controls systems,  air treatment, and other miscellaneous work for the Fair Park Coliseum Facility Improvements Project located at 1438 Coliseum Drive - Not to exceed $851,357.27, from $10,138,840.87 to $10,990,198.14‬ - Financing: Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund) ‬‬‬‬‬‬‬‬‬‬

 

Body

BACKGROUND

 

The original scope of work consisted of renovation to the Fair Park Coliseum, constructed in 1958. The work included improvements to the mechanical, electrical distribution and lighting systems. The work also included a new fire alarm system, replacement of all the seating in the arena as well as improvements to the interior ramps and site paving for compliance with the Americans with Disabilities Act, in an amount not to exceed $10,042,531.00.

 

On August 19, 2020, Administrative Action No. 20-1068 authorized Change Order No. 1 to the construction services contract with Azteca Enterprises, Inc. for additional scope of work for the Fair Park Coliseum Facility Improvements Project to include deletions of seating fabric and mechanical system demolition as well as additions to the electrical system, in an amount not to exceed $46,581.77, from $10,042,531.00 to $10,089,112.77.

 

On September 29, 2020, Administrative Action No. 20-1196 authorized Change Order No. 2 to the construction services contract with Azteca Enterprises, Inc. for additional scope of work for the Fair Park Coliseum Facility Improvements Project to include additional seating in the arena, rerouting a storm line, upgrades to proposed exit signs as well as electrical conduit, feeders and disconnect for an additional transformer, in an amount not to exceed $49,728.10, from $10,089,112.77 to $10,138,840.87.

 

 

This action will authorize Change Order No. 3 to the construction services contract with Azteca Enterprises, Inc. for additional scope of work for the Fair Park Coliseum Facility Improvements Project. The additional scope of work includes including upgrades to the fire alarm, electrical distribution panels, heating, ventilation, and air conditioning controls systems, bipolar ionization air treatment for better indoor air quality and other miscellaneous work.

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On November 21, 2019, the Park and Recreation Board authorized a construction contract with Azteca Enterprises, Inc. for the Fair Park Coliseum Facility Improvements Project located at 1438 Coliseum Drive.

 

On February 26, 2020, City Council authorized a construction contract with Azteca Enterprises, Inc. for the construction of the Fair Park Coliseum Facility Improvements Project located at 1438 Coliseum Drive by Resolution No. 20-0370.

 

On December 10, 2020, the Park and Recreation Board authorized an increase in the construction services contract with Azteca Enterprises, Inc. for additional scope of work for construction of the Fair Park Coliseum Facility Improvements Project located at 1438 Coliseum Drive.

 

FISCAL INFORMATION

 

Fund

FY 2020

FY 2021

Future Years

Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund)

$851,357.27

$0.00

$0.00

 

Construction Contract                      $10,042,531.00

Change Order No. 1                      $       46,581.77

Change Order No. 2                     $       49,728.10

Change Order No. 3 (this action)                     $     851,357.27

 

                     Total                                          $10,990,198.14

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$851,357.27

Construction

25.00%*

81.63%

$694,954.60

*This item reflects previous Business Inclusion and Development Policy M/WBE goal.

This contract exceeds the M/WBE goal.

Change Order No. 3 - 67.48% overall M/WBE participation

Azteca Enterprises, Inc. - Local; Workforce - 54.55% Local

OWNER

 

Azteca Enterprises, Inc.

 

Luis Spinola, President/Chief Executive Officer

 

MAP

 

Attached