Dallas Logo
File #: 20-2521    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 12/23/2020 In control: Building Services Department
On agenda: 1/27/2021 Final action:
Title: Authorize a work order under the existing Job Order Contract, previously approved on January 9, 2019, by Resolution No. 19-0074 for construction services with Brown & Root Industrial Services, LLC for structural repairs at Fire Station No. 30 located at 11381 Zodiac Lane - Not to exceed $650,000.00 - Financing: Capital Construction Fund
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: January 27, 2021
COUNCIL DISTRICT(S):|910|DEPARTMENT: Building Services Department
EXECUTIVE: Joey Zapata
______________________________________________________________________
SUBJECT

Title
Authorize a work order under the existing Job Order Contract, previously approved on January 9, 2019, by Resolution No. 19-0074 for construction services with Brown & Root Industrial Services, LLC for structural repairs at Fire Station No. 30 located at 11381 Zodiac Lane - Not to exceed $650,000.00 - Financing: Capital Construction Fund

Body
BACKGROUND

In October 2019, cracks were observed in the brick walls and the foundation slab of the apparatus bay at Fire Station No. 30. The cracks widened and caused wall shifting, settlement and falling brick veneers. The conditions presented a safety risk to the occupants and the Building Services Department recommended the station be vacated in November 2019 and a geotechnical engineering distress and structural integrity review was ordered for Fire Station No. 30 to determine the condition and the options available for corrective action.

The testing confirmed that the soils in this area are relatively active and the piles installed with the station's construction were found to not be as deep as indicated on the design plans. The final recommendation for repairs is to provide additional piling under the grade beam of the north wall, repair the north wall, and repair the slab in the apparatus bay.

The estimated construction cost for this project is based on the preliminary geotechnical engineering distress and structural integrity review and through comparisons to other projects involving similar foundation repair work. Job Order amounts are determined using an industry standard construction price book (RS Means - Facilities Construction Cost Data) and City discounts per the contract.

Job Order Contracting (JOC) is an alternative contrac...