Dallas Logo
File #: 21-48    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 1/13/2021 In control: Park & Recreation Department
On agenda: 2/10/2021 Final action:
Title: Authorize a construction services contract for the construction of the Westmount Park Site Development Project located at 1300 Westmount Avenue - A S Con, Inc., lowest responsible bidder of seven - Not to exceed $153,400.00 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund)
Indexes: 1
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life

AGENDA DATE:                     February 10, 2021

COUNCIL DISTRICT(S):                     1

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     John D. Jenkins

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the construction of the Westmount Park Site Development Project located at 1300 Westmount Avenue - A S Con, Inc., lowest responsible bidder of seven - Not to exceed $153,400.00 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund)

 

Body

BACKGROUND

 

On October 23, 2020, seven bids were received for the construction of the Westmount Park Site Development Project. This item authorizes the award of this construction services contract to A S Con, Inc., lowest responsible bidder of seven for the Base Bid and Alternate No. 1 in the amount of $153,400.00.

 

The scope of work for the Westmount Park Site Development Project includes construction of playground improvements including fencing, grading, and establishment of ground cover.

 

The following chart illustrates A S Con, Inc.’s, contractual activities with the City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                                          0                     0                                          2                                          0

Active Projects                                          0                     0                                          0                                          0

Change Orders                                           0                     0                                          2                                          0

Projects Requiring Liquidated Damages                                          0                     0                                          0                                          0

Projects Completed by Bonding Company                                          0                     0                                          0                                          0

 

 

 

 

Estimated Schedule of Project

 

Began Design                                          April 2019

Completed Design                                          September 2020

Begin Construction                                          March 2021

Complete Completion                      August 2021

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On September 17, 2020, the Park and Recreation Board, Planning and Design Committee was briefed on construction procurement.

 

On January 28, 2021, the Park and Recreation Board authorized a construction contract with A S Con Inc. for the construction of the Westmount Park Site Development Project located at 1300 Westmount Avenue.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund)

$153,400.00

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$153,400.00

Construction

32.00%

25.29%

$38,800.00

This contract does not meet the M/WBE goal, but complies with good faith efforts.

A S Con Inc. - Local; Workforce - 100.00% Local

 

PROCUREMENT INFORMATION

 

The following seven bids were received and opened on October 23, 2020:

 

*Denotes successful bidder

                                                                

Bidders                     Base Bid                     Alternate No. 1**                     Total Bid

                                                               

*A S Con, Inc.                     $  63,600.00                     $ 89,800.00                                          $153,400.00

 15724 Golden Creek Road

 Dallas, Texas 75248

North Rock Construction                     $  95,425.72                     $  69,796.23                                          $165,221.95

Aleksander Omega, LLC                     $  95,146.00                     $  90,000.00                                          $185,146.00

JB & Co. LLC                     $  79,954.25                     $110,000.00                                          $189,954.25

Quick Set Concrete Inc.                     $  99,833.55                     $101,000.00                                          $200,833.55

Henneberger Construction, Inc.                     $109,740.80                     $114,000.00                                          $223,740.80

Northstar Construction, LLC                     $105,984.00                     $126,500.00                                          $232,484.00

 

**Alternate No. 1 - provides for the installation of Dynamo playground equipment.

 

OWNER

 

A S Con, Inc.

 

Ali Safdarinia, President

 

MAP

 

Attached