STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: February 24, 2021
COUNCIL DISTRICT(S): 2, 7, 14
DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with Southland Mole JV for additional work associated with additional tunnel support, paving, storm drainage, water and wastewater improvements for the Mill Creek / Peaks Branch / State-Thomas Drainage Relief Tunnel Project - Not to exceed $3,332,735.00, from $206,700,000.00 to $210,032,735.00 - Financing: Flood Protection and Storm Drainage Facilities Fund (2006 General Obligation Funds) ($3,242,535.00), Water Capital Improvement D Fund ($79,000.00) and Wastewater Capital Improvement E Fund ($11,200.00)
Body
BACKGROUND
The 2006 and 2012 Bond Programs provided funding for design and construction of storm drainage relief improvements for the Mill Creek / Peaks Branch / State-Thomas watersheds. On February 14, 2018, City Council authorized a construction contract with Southland Mole JV., for the construction of the Mill Creek / Peaks Branch / State-Thomas Drainage Relief Tunnel Project by Resolution No. 18-0296. The project includes a 5-mile tunnel that will provide drainage and flooding relief to the lower areas of the Mill Creek watershed (around Baylor Hospital), Peaks Branch watershed (south of Buckner Park), and East Peaks Branch watershed (around Fair Park area). It will also provide drainage and flooding relief to the State-Thomas area near Woodall Rodgers.
This action will authorize Change Order No. 1 to the construction services contract with Southland Mole JV for repairs and improvements to existing storm drainage systems directly connected with the Mill Creek tunnel system and increased quantities for tunnel support, paving restoration, water, and wastewater improvements. The repairs and improvements to existing drainage systems are necessary to address failed infrastructure and conveyance limitations directly upstream of tunnel intake points. Increased quantities for changed site conditions include welded wire mesh, rock bolts, reinforced concrete pavement and sidewalk, water and wastewater pipe. No additional contract time is included with this change order.
ESTIMATED SCHEDULE OF PROJECT
Began Construction February 2018
Complete Construction March 2023
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On February 14, 2018, City Council authorized a construction contract with Southland Mole JV., for the construction of Mill Creek / Peaks Branch / State-Thomas Drainage Relief Tunnel project by Resolution No. 18-0296.
FISCAL INFORMATION
Fund |
FY 2021 |
FY 2022 |
Future Years |
Flood Protection and Storm Drainage Facilities Fund (2006 General Obligation Funds) |
$3,242,535.00 |
$0.00 |
$0.00 |
Water Capital Improvement D Fund |
$ 79,000.00 |
$0.00 |
$0.00 |
Wastewater Capital Improvement E Fund |
$ 11,200.00 |
$0.00 |
$0.00 |
Total |
$3,332,735.00 |
$0.00 |
$0.00 |
Construction $206,700,000.00
Change Order No. 1 (this action) $ 3,332,735.00
Total Project Cost $210,032,735.00
Council District Amount
2 $ 899,757.00
7 $1,499,488.00
14 $ 933,130.00
Total $3,332,375.00
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
M/WBE % |
M/WBE $ |
$3,332,735.00 |
Construction |
25.00%* |
25.40% |
$846,590.00 |
• *This item reflects previous Business Inclusion and Development Policy M/WBE goal. |
• This contract exceeds the M/WBE goal. |
• Change Order No. 1 - 32.43% Overall M/WBE participation |
• Southland Mole JV - Non Local; Workforce - 28.00% Local |
OWNER
Southland Mole JV
Frank Renda, Director/Principal
MAP
Attached