File #: 20-895    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 4/30/2020 In control: Department of Public Works
On agenda: 4/14/2021 Final action:
Title: Authorize a decrease to the construction services contract with Texas Standard Company, Ltd. to compensate the contractor for remobilization and four months of traffic control for delays experienced due to relocation of utility conflicts and delete some work items from the traffic signal and urban design scope for the reconstruction and complete street improvements along Gus Thomasson Road from San Medina Avenue to Ferguson Road - Not to exceed ($263,360.00), decreasing the contract amount from $4,381,903.88 to $4,118,543.88 - Financing: Street and Transportation Improvements Fund (2012 General Obligation Bond Fund) (-$110,625.00) and Specified Streets Project Fund (2003 General Obligation Bond Fund) (-$152,735.00)
Indexes: 9
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     April 14, 2021

COUNCIL DISTRICT(S):                     9

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize a decrease to the construction services contract with Texas Standard Company, Ltd. to compensate the contractor for remobilization and four months of traffic control for delays experienced due to relocation of utility conflicts and delete some work items from the traffic signal and urban design scope for the reconstruction and complete street improvements along Gus Thomasson Road from San Medina Avenue to Ferguson Road - Not to exceed ($263,360.00), decreasing the contract amount from $4,381,903.88 to $4,118,543.88 - Financing: Street and Transportation Improvements Fund (2012 General Obligation Bond Fund) (-$110,625.00) and Specified Streets Project Fund (2003 General Obligation Bond Fund) (-$152,735.00)

 

Body

BACKGROUND

 

On February 22, 2017, City Council authorized a construction contract with Texas Standard Construction, Ltd., for the reconstruction of street paving, storm drainage, traffic signal, landscaping and water and wastewater main improvements along Gus Thomasson Road from San Medina Avenue to Ferguson Road by Resolution No. 17- 0439.

 

During construction, unforeseen field conditions and utility conflicts were encountered that made it difficult for the contractor to complete the proposed traffic signal and urban design scope for this project. Consequently, the project completion was delayed, and the decision was made to remove this remaining work from the contract and have it completed by the Transportation Department and City forces.

 

This action will authorize a decrease to the construction services contract with Texas Standard Construction, Ltd. to compensate the contractor for remobilization and four months of traffic control for delays experienced due to relocation of utility conflicts and delete some work items from the traffic signal and urban design scope for the reconstruction and complete street improvements along Gus Thomasson Road from San Medina Avenue to Ferguson Road.

 

Texas Standard Construction, Ltd. is a Dallas-based corporation, operating within the corporate city limits of Dallas, Texas.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction:                      August 2017

Complete Construction:                     May 2021

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On February 22, 2017, City Council authorized the construction services contract with Texas Standard Construction, Ltd., for the reconstruction and complete street improvements along Gus Thomasson Road from San Medina Avenue to Ferguson Road by Resolution No. 17-0439.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Street and Transportation Improvements Fund (2012 General Obligation Bond Fund)

(-$110,625.00)

$0.00

$0.00

Specified Streets Project Fund (2003 General Obligation Bond Fund)

(-$152,735.00)

$0.00

$0.00

Total

(-$263,360.00)

$0.00

$0.00

 

Construction contract                     $4,216,721.95

Change Order No. 1                      $     10,682.00

Change Order No. 2                      $     49,000.00

Change Order No. 3                      $       5,556.93

Change Order No. 4                      $     49,998.00

Change Order No. 5                      $     49,945.00

Change Order No. 6 (this action)        ($  263,360.00)

 

Project Total                     $4,118,543.88

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

(-$263,360.00)

Construction

25.00%*

0.00%

$0.00

*This item reflects previous Business Inclusion and Development Policy goal.

This contract does not meet the M/WBE goal, but complies with good faith efforts.

Texas Standard Company, Ltd. - Local

 

 

 

OWNER

 

Texas Standard Company, Ltd.

 

Ronald H. Dalton, President

 

MAP

 

Attached