Title: Authorize an increase to the construction services contract with DDM Construction Corporation to allow for additional removal of concrete pavement for Street Reconstruction Group 17-6001 (list attached to the Agenda Information Sheet) - Not to exceed $390,996.63, from $4,181,920.70 to $4,572,917.33 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)
Indexes: 2, 6
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     April 14, 2021

COUNCIL DISTRICT(S):                     2, 6

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase to the construction services contract with DDM Construction Corporation to allow for additional removal of concrete pavement for Street Reconstruction Group 17-6001 (list attached to the Agenda Information Sheet) - Not to exceed $390,996.63, from $4,181,920.70 to $4,572,917.33 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

 

Body

BACKGROUND

 

Due to unforeseen field conditions, the quantities of bid item 201- REMOVE CONCRETE PAVEMENT, DRIVE AND APRON will substantially exceed the original calculated amount. The construction documents do not show reinforced concrete pavement underneath the asphalt road since the bore logs that were provided by the geotechnical investigation do not illustrate any reinforced concrete underneath the roadway. The bid quantities were accounted for as unclassified street excavation for Street Reconstruction Group 17-6001.

 

This action will authorize payment for all additional concrete removals needed to complete the project.

 

Delays in processing the change order will lead to payment interruption to the contractor.

 

Following are the locations and costs for each project:

 

Street Reconstruction - Local Streets - Improvements

 

Project                     Council District                     Amount

 

Lenel Place (Partnership with District 2)

from Clover Lane to Wemdon Drive                     2                     $  95,554.80

Wemdon Drive                     6                     $107,499.15

 

Lenel Place from Lively Lane

to Clover Lane                     6                     $  97,598.25

 

Lenel Place from Wemdon Drive

to Mixon Drive                     6                     $  90,344.43

 

DDM Construction Corporation is a registered vendor with the City and has an office in Addison, Texas.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                     July 2020

Complete Construction                     October 2021

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On December 11, 2019, City Council authorized a construction contract with DDM Construction Corporation by Resolution No. 19-1878.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

$390,996.63

$0.00

$0.00

 

Construction Contract                                                               $4,181,920.70

Change Order No. 1 (this action)                                                               $   390,996.63

 

Project Total                     $4,572,917.33

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$390,996.63

Construction

32.00%

5.43%

$21,245.96

This contract does not meet the M/WBE goal, but complies with good faith efforts.

Change Order No. 1 - 53.80% Overall MWBE participation

DDM Construction Corp. - Non - Local; Workforce - 28.00% Local

 

OWNER

 

DDM Construction Corp.

 

Zackery Markwardt, Vice President

 

MAPS

 