Dallas Logo
File #: 21-680    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 4/5/2021 In control: Water Utilities Department
On agenda: 6/9/2021 Final action:
Title: Authorize a construction services contract for (1) an eighteen-month master agreement for water and wastewater small services installations in the amount of $5,340,775.00; (2) the installation of water and wastewater mains at four locations in the amount of $2,571,487.50 (list attached to the Agenda Information Sheet); and (3) an eighteen-month master agreement for water and wastewater mainline extensions and emergency mainline installations and relocations at various locations in the amount of $2,645,375.00 - Total not to exceed $10,557,637.50 - Douglas Dailey Construction, LLC, lowest bidder of three - Financing: Water Construction Fund ($5,414,338.75) and Wastewater Construction Fund ($5,143,298.75)
Indexes: 100
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     June 9, 2021

COUNCIL DISTRICT(S):                     All

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for (1) an eighteen-month master agreement for water and wastewater small services installations in the amount of $5,340,775.00; (2) the installation of water and wastewater mains at four locations in the amount of $2,571,487.50 (list attached to the Agenda Information Sheet); and (3) an eighteen-month master agreement for water and wastewater mainline extensions and emergency mainline installations and relocations at various locations in the amount of $2,645,375.00 - Total not to exceed $10,557,637.50 - Douglas Dailey Construction, LLC, lowest bidder of three - Financing: Water Construction Fund ($5,414,338.75) and Wastewater Construction Fund ($5,143,298.75)

 

Body

BACKGROUND

 

Part One of this action, in the amount of $5,340,775.00, consists of a small services 18-month master agreement for the installation of 3/4 inch to 2-inch water services and 6-inch wastewater connections, as requested by the Sustainable Development and Construction Department, upon issuance of a permit to the property owner.

 

Part Two of this action, in the amount of $2,571,487.50, includes the installation of approximately 30 feet of 4-inch, 280 feet of 6-inch, and 2,640 feet of 8-inch water mains, and the installation of approximately 2,920 feet of 8-inch, and 1,120 feet of 12-inch wastewater mains. The existing water and wastewater mains were built between 1926 and 1968. These mains are contributing to an increase in maintenance costs, as well as service interruptions. The installation of the proposed segments will improve the capacity of the water and wastewater systems and reduce maintenance costs.

 

Part Three of this action, in the amount of $2,645,375.00, includes water and wastewater mainline extensions and consists of an 18-month master agreement in support of small services that may require extension of the existing mainlines. Also included are water and wastewater emergency mainline replacements and relocations, which will allow for quick response in support of Dallas Water Utilities’ operations.

 

The following chart illustrates Douglas Dailey Construction, LLC’s contractual activities with the City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     0                     0                     0                                             0

Active Projects                     0                     1                     0                                             0

Change Orders                     0                     0                     0                                             0

Projects Requiring Liquidated Damages                     0                     0                     0                                             0

Projects Completed by Bonding Company                     0                     0                     0                                             0

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     August 2021

Complete Construction                     February 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Water Construction Fund

$  5,414,338.75

$0.00

$0.00

Wastewater Construction Fund

$  5,143,298.75

$0.00

$0.00

Total

$10,557,637.50

$0.00

$0.00

                     

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$10,557,637.50

Construction

32.00%

40.22%

$4,245,775.00

This contract exceeds the M/WBE goal.

Douglas Dailey Construction, LLC - Non-local; Workforce - 22.86% Local

 

 

 

 

 

 

 

 

PROCUREMENT INFORMATION

 

The following three bids with quotes were received and opened on March 19, 2021:

 

*Denotes successful bidder

 

Bidder                     Bid Amount

 

*Douglas Dailey Construction, LLC                      $10,557,637.50

  2005 Bluff Springs Road

  Ferris, Texas 75215                     

Omega Contracting, Inc.                     $11,498,945.25

Canary Construction, Inc.                     $12,494,514.00

 

OWNER

 

Douglas Dailey Construction, LLC

 

Douglas Dailey, Owner

 

MAPS

 

Attached