File #: 21-787    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 4/22/2021 In control: Water Utilities Department
On agenda: 6/23/2021 Final action:
Title: Authorize a construction services contract for residual handling improvements at the East Side Water Treatment Plant - BAR Constructors, Inc., lowest responsible bidder of five - Not to exceed $27,335,500.00 - Financing: Water Capital Improvement D Fund
Indexes: 200
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     June 23, 2021

COUNCIL DISTRICT(S):                     Outside City Limits

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for residual handling improvements at the East Side Water Treatment Plant - BAR Constructors, Inc., lowest responsible bidder of five - Not to exceed $27,335,500.00 - Financing: Water Capital Improvement D Fund

 

Body

BACKGROUND

 

The East Side Water Treatment Plant (ESWTP) was originally constructed in the 1960s and is the largest of three water treatment plants serving customers of the City of Dallas Water Utilities Department (DWU) with a treatment capacity of 440 million gallons per day.  The most recent construction improvement projects at the plant have implemented process modifications recommended by a DWU Water Quality Study to increase the chemical and biological stability of the finished water.

 

The Water Quality Study also recommended improvements to the handling of residuals which are a normal byproduct of the water treatment process.  These recommended improvements will be designed and constructed in phases at the ESWTP.  Once completed, they will allow for the separation of residual streams and will improve the quality of water recycled in the plant.  In turn, this will improve the efficiency of the treatment process and allow for a more continuous and consistent residual handling operation.  Since the early 1990s, ESWTP has primarily used a system of five on-site lagoons for residual management.  The existing lagoons are nearing their ultimate capacity and the construction of new residual handling facilities will extend their useful life and provide flexibility in the future operational use of the lagoons.

 

This action will authorize construction of the first phase of new residual handling facilities at the ESWTP.  Improvements in the first phase include the construction of two new lagoons, a permanent structural concrete pad for dewatering of residuals removed from the lagoons, the repurposing of an existing facility as a temporary residuals pump station and associated civil and mechanical improvements to connect the new lagoon system.  The project also includes plant drain modifications for implementation of the recommended separation of residual streams, fencing around the new facilities, permanent slope repairs and regrading around the existing lagoons, and the installation of permanent slope protection in the area of the repairs.  Future phases will be implemented based on priorities that are being developed as part of an on-going water production strategic plan.

 

The following chart illustrates BAR Constructors, Inc.’s contractual activities with the City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     0                     0                     0                     0

Active Projects                     0                     3                     0                     0

Change Orders                     0                     2                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          August 2021

Complete Construction                     July 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Water Capital Improvement D Fund

$27,335,500.00

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$27,335,500.00

Construction

32.00%

49.56%

$13,547,467.00

This contract exceeds the M/WBE goal.

BAR Constructors, Inc. - Non-local; Workforce - 4.30% Local

 

PROCUREMENT INFORMATION

 

The following five bids with quotes were received and opened on March 26, 2021:

 

*Denotes successful bidder

 

Bidders                     Bid Amount

 

*BAR Constructors, Inc.                     $27,335,500.00

  805 Katy Street

  Lancaster, Texas 75146

The Whiting Turner Contracting Company                     $30,853,098.00

Archer Western Construction, LLC                     $30,970,000.00

Ark Contracting Services, LLC                     $32,538,000.00

Oscar Renda Contracting, Inc.                     $33,160,000.00

 

OWNER

 

BAR Constructors, Inc.

 

Isidro Arrambide, Jr., President

 

MAP

 

Attached