Dallas Logo
File #: 21-969    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 5/13/2021 In control: Department of Public Works
On agenda: 6/23/2021 Final action:
Title: Authorize (1) an Interlocal Agreement with County of Collin, Texas ("Collin County") for funding participation of transportation-related improvements of Frankford Road from State Highway 289 (Preston Road) to Coit Road in Dallas; (2) the receipt and deposit of funds from Collin County in an amount not to exceed $2,677,326.00 in the Capital Projects Reimbursement Fund; and (3) an increase in appropriations in an amount not to exceed $2,677,326.00 in the Capital Projects Reimbursement Fund - Not to exceed $2,677,326.00 - Financing: Capital Projects Reimbursement Fund
Indexes: 12
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     June 23, 2021

COUNCIL DISTRICT(S):                     12

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

title

Authorize (1) an Interlocal Agreement with County of Collin, Texas (“Collin County”) for funding participation of transportation-related improvements of Frankford Road from State Highway 289 (Preston Road) to Coit Road in Dallas; (2) the receipt and deposit of funds from Collin County in an amount not to exceed $2,677,326.00 in the Capital Projects Reimbursement Fund; and (3) an increase in appropriations in an amount not to exceed $2,677,326.00 in the Capital Projects Reimbursement Fund - Not to exceed $2,677,326.00 - Financing:  Capital Projects Reimbursement Fund

 

body

BACKGROUND

 

This action will authorize an Interlocal Agreement with Collin County for funding participation for thoroughfare improvements to Frankford Road from State Highway 289 (Preston Road) to Coit Road.  This project was selected as part of the 2019/2020 Collin County Call for City Projects and is a partnership project between the City of Dallas and Collin County for transportation-related maintenance, repairs, and improvements.  The City of Dallas is the lead agency responsible for administering design and construction of the project.

 

The project will consist of reconstructing Frankford Road (a six-lane-divided arterial) from State Highway 289 (Preston Road) to Coit Road by performing base repair and asphalt overlay, curb and gutter replacement where needed, pavement markings, and traffic sign replacement, and upgrading the traffic signals at the intersections of Frankford Road at Davenport Road, Hillcrest Road, Meandering Way, Preston Ridge Trail and Osage Plaza Parkway. Also, pedestrian improvements such as sidewalks, driveway approaches, barrier-free-ramps, crosswalk enhancements, streetlights, benches, trash receptacles, bike racks, and other minor landscaping and irrigation improvements will be included as part of the project scope.

 

The total estimated project cost for design is $495,585.00. Estimated construction cost is $6,617,705.00, of which $2,677,326.00 is to be funded by Collin County, and the remaining cost is to be funded by the City of Dallas.

ESTIMATED SCHEDULE OF PROJECT

 

Begin Design                                           August 2021

Complete Design                                          August 2022

Begin Construction                                          December 2022

Complete Construction                     December 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Capital Projects Reimbursement Fund

$2,677.326.00

$0.00

$0.00

 