STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 9, 2021
COUNCIL DISTRICT(S): 6
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
Title
Authorize a construction services contract for the construction of Street Reconstruction Group 17-6006 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of seven - Not to exceed $2,255,809.03 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($1,490,634.98), Water Construction Fund ($16,700.00), Water Capital Improvement D Fund ($511,805.00), Wastewater Construction Fund ($22,900.00), and Wastewater Capital Improvement E Fund ($213,769.05)
Body
BACKGROUND
This action will authorize a construction services contract with Estrada Concrete Company, LLC for the construction of three local street reconstruction projects as Street Reconstruction Group 17-6006.
The project scope will include replacing the existing deteriorating concrete streets with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, drainage system, and water and wastewater improvements.
Estrada Concrete Company, LLC is a Dallas-based corporation, operating within the corporate city limits of Dallas, Texas.
Following are the locations and construction costs for each project:
Project Council District Amount
Babcock Drive from Bernal Drive
to Canada Drive 6 $634,241.05
Halifax Street from Cash Road
to Pulaski Street 6 $680,914.98
Quebec Street from Sharp Street
to Mockingbird Lane 6 $940,653.00
The following chart illustrates Estrada Concrete Company, LLC’s contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TRN
Projects Completed 0 0 0 0
Active Projects 10 1 0 0
Change Orders 2 0 0 0
Projects Requiring Liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0
If this project group is not awarded for construction at this time, the streets will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicles utilizing the streets. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.
ESTIMATED SCHEDULE OF PROJECT
Begin Construction November 2021
Complete Construction September 2023
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
Fund |
FY 2021 |
FY 2022 |
Future Years |
Street and Transportation (A) Fund (2017 General Obligation Bond Fund) |
$1,490,634.98 |
$0.00 |
$0.00 |
Water Construction Fund |
$ 16,700.00 |
$0.00 |
$0.00 |
Water Capital Improvement D Fund |
$ 511,805.00 |
$0.00 |
$0.00 |
Wastewater Construction Fund |
$ 22,900.00 |
$0.00 |
$0.00 |
Wastewater Capital Improvement E Fund |
$ 213,769.05 |
$0.00 |
$0.00 |
Total |
$2,255,809.03 |
$0.00 |
$0.00 |
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
M/WBE % |
M/WBE $ |
$2,255,809.03 |
Construction |
32.00% |
100.00% |
$2,255,809.03 |
• This contract exceeds the M/WBE goal. |
• Estrada Concrete Company, LLC - Non-local; Workforce - 67.00% Local |
PROCUREMENT INFORMATION
The following seven bids were received and opened on June 4, 2021:
*Denotes successful bidder
Bidders Bid Amount
*Estrada Concrete Company, LLC $2,255,809.03
1623 Garza Avenue
Dallas, TX 75216
Jeske Construction Company $2,401,659.00
Camino Construction $2,444,145.00
Vescorp Construction, LLC dba $2,589,002.50
Chavez Concrete Cutting
Tiseo Paving Company $2,936,382.00
Axis Contracting, Inc. $2,994,683.00
HQS Construction $3,064,186.00
OWNER
Estrada Concrete Company, LLC
David Bowers, Vice President
MAPS
Attached