Dallas Logo
File #: 21-1385    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 7/26/2021 In control: Water Utilities Department
On agenda: 9/9/2021 Final action:
Title: Authorize an increase in the construction services contract with Oscar Renda Contracting, Inc. for additional work associated with the construction of biological filtration optimization improvements at the East Side Water Treatment Plant - Not to exceed $1,225,387.90, from $24,904,983.00 to $26,130,370.90 - Financing: Water Capital Improvement D Fund
Indexes: 200
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 9, 2021
COUNCIL DISTRICT(S): Outside City Limits
DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with Oscar Renda Contracting, Inc. for additional work associated with the construction of biological filtration optimization improvements at the East Side Water Treatment Plant - Not to exceed $1,225,387.90, from $24,904,983.00 to $26,130,370.90 - Financing: Water Capital Improvement D Fund

Body
BACKGROUND

East Side Water Treatment Plant was originally constructed in the 1960s and is the largest of three water treatment plants serving customers of the City of Dallas Water Utilities Department (DWU) with a treatment capacity of 440 million gallons per day. The most recent construction improvement projects were recommended by a DWU Water Quality Study to increase the chemical and biological stability of the finished water.

The biological filtration improvements project augments the existing filter facilities for biological removal of organics and includes a new backwash pump station and chemical storage and feed facilities. Pump station improvements will allow the filters to be backwashed with non-chlorinated water to encourage biological activity in the filters. Chemical storage and feed facilities allow the introduction of process chemicals which improve the desired biological activity, optimizing the removal of organics.

This action will authorize Change Order No. 1 to the construction services contract, to the contract with Oscar Renda Contracting, Inc. for additional work identified during the construction of the pump station and chemical facilities. Excavation for the pump station uncovered unknown structures that had to be removed prior to construction of the wetwell, and the backwash pump statio...