Title: Authorize a construction services contract for the construction of Street Reconstruction Group 17-8001 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of four - Not to exceed $746,935.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($681,305.00), Water Construction Fund ($3,200.00), and Water Capital Improvement D Fund ($62,430.00)
Indexes: 8
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     September 22, 2021

COUNCIL DISTRICT(S):                     8

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the construction of Street Reconstruction Group 17-8001 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of four - Not to exceed $746,935.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($681,305.00), Water Construction Fund ($3,200.00), and Water Capital Improvement D Fund ($62,430.00)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with Estrada Concrete Company, LLC for the construction of four street reconstruction projects as Street Reconstruction Group 17-8001.

 

The scope of the project group includes the construction of reinforced concrete pavement, replacement of the existing asphalt with new asphalt pavement, replacement of on-street parking spaces, sidewalks, mountable curbs, driveway approaches, curbs and gutters, storm drainage improvements, and water improvements.

 

Estrada Concrete Company, LLC is a Dallas-based corporation, operating within the corporate city limits of Dallas, Texas.

 

Following are the locations and construction cost for each project:

 

Project                     Council District                     Amount

 

Laurel Hill Drive from Budeudy Drive

to End of Pavement                      8                     $  30,175.00

 

Laurel Hill Drive from Kleberg Road

to Budeudy Drive                      8                     $280,525.00

 

Oak Plaza Place from Kleberg Road

to End of Pavement                     8                     $272,575.00

 

Park Manor Drive from Simpson Stuart Road

to Happy Canyon Drive                     8                     $163,660.00

 

The following chart illustrates Estrada Concrete Company, LLC contractual activities with the City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     0                     0                     0                     0

Active Projects                       10                     1                     0                     0

Change Orders                     2                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

If this project group is not awarded for construction at this time, the roadways will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicles utilizing the roadways.  Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          November 2021

Complete Construction                     May 2022

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2021

FY 2022

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Funds)

$ 681,305.00

$0.00

$0.00

Water Construction Fund

$     3,200.00

$0.00

$0.00

Water Capital Improvement D Fund

$   62,430.00

$0.00

$0.00

Total

$ 746,935.00

$0.00

$0.00

 

 

 

 

 

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$746,935.00

Construction

32.00%

100.00%

$746,935.00

This contract exceeds the M/WBE goal.

Estrada Concrete Company, LLC - Non-local; Workforce - 67.00% Local

 

PROCUREMENT INFORMATION

 

The following four bids were received and opened on June 25, 2021:

 

*Denotes successful bidder

 

Bidders                                                                                                           Bid Amount

 

*Estrada Concrete Company, LLC                     $   746,935.00

 1623 Garza Avenue

 Dallas, Texas, 75216

HQS Construction, LLC                                                                                                         $   823,842.10

MACVAL Associations, LLC                                                                                    $   997,005.75

Camino Construction, L.P.                                                                                                         $1,033,265.00

 

OWNER

 

Estrada Concrete Company, LLC

 

David W. Bowers, Vice President

 

MAPS

 

Attached