Authorize a construction services contract for the construction of Street Reconstruction Group 17-8001 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of four - Not to exceed $746,935.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($681,305.00), Water Construction Fund ($3,200.00), and Water Capital Improvement D Fund ($62,430.00)
Body
BACKGROUND
This action will authorize a construction services contract with Estrada Concrete Company, LLC for the construction of four street reconstruction projects as Street Reconstruction Group 17-8001.
The scope of the project group includes the construction of reinforced concrete pavement, replacement of the existing asphalt with new asphalt pavement, replacement of on-street parking spaces, sidewalks, mountable curbs, driveway approaches, curbs and gutters, storm drainage improvements, and water improvements.
Estrada Concrete Company, LLC is a Dallas-based corporation, operating within the corporate city limits of Dallas, Texas.
Following are the locations and construction cost for each project:
Project Council District Amount
Laurel Hill Drive from Budeudy Drive
to End of Pavement 8 $ 30,175.00
Laurel Hill Drive from Kleberg Road
to Budeudy Drive 8 $280,525.00
Oak Plaza Place from Kleberg Road
to End of Pavement 8 $272,575.00
Park Manor Drive from Simpson Stuart Road
to Happy Canyon Drive 8 $163,660.00
The following chart illustrates Estrada Concrete Company, LLC contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TRN
Projects Completed 0 0 0 0
Active Projects 10 1 0 0
Change Orders 2 0 0 0
Projects Requiring Liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0
If this project group is not awarded for construction at this time, the roadways will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicles utilizing the roadways. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.
ESTIMATED SCHEDULE OF PROJECT
Begin Construction November 2021
Complete Construction May 2022
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
Fund |
FY 2021 |
FY 2022 |
Future Years |
Street and Transportation (A) Fund (2017 General Obligation Bond Funds) |
$ 681,305.00 |
$0.00 |
$0.00 |
Water Construction Fund |
$ 3,200.00 |
$0.00 |
$0.00 |
Water Capital Improvement D Fund |
$ 62,430.00 |
$0.00 |
$0.00 |
Total |
$ 746,935.00 |
$0.00 |
$0.00 |
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
M/WBE % |
M/WBE $ |
$746,935.00 |
Construction |
32.00% |
100.00% |
$746,935.00 |
• This contract exceeds the M/WBE goal. |
• Estrada Concrete Company, LLC - Non-local; Workforce - 67.00% Local |
PROCUREMENT INFORMATION
The following four bids were received and opened on June 25, 2021:
*Denotes successful bidder
Bidders Bid Amount
*Estrada Concrete Company, LLC $ 746,935.00
1623 Garza Avenue
Dallas, Texas, 75216
HQS Construction, LLC $ 823,842.10
MACVAL Associations, LLC $ 997,005.75
Camino Construction, L.P. $1,033,265.00