STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: October 27, 2021
COUNCIL DISTRICT(S): 2, 3, 9, 10, 14
DEPARTMENT: Department of Transportation
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
Title
Authorize a construction services contract for the Warranted Traffic Signal Installation Group 9, for traffic signal construction at the following five locations: Abrams Road at Lakeshore Drive; Miller Road at Rockwall Road; Timberline Drive at Webb Chapel Ext; Fort Worth Avenue at Pinnacle Park Boulevard; and West Kiest Boulevard at Pierce Street - Roadway Solutions, Inc., lowest responsible bidder of three - Not to exceed $1,377,765.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds)
Body
BACKGROUND
This action will authorize a construction contract with Roadway Solutions, Inc., lowest responsible bidder of three, to construct five traffic signals as part of services for the Warranted Traffic Signal Installations - Group 9 Project.
Bid specifications were developed and publicly advertised on June 9, 2021, and June 16, 2021, for competitive bids associated with the Warranted Traffic Signal Installations - Group 9 Project. Bids were opened on July 16, 2021.
The following chart illustrates Roadway Solutions, Inc.'s contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TRN
Current Projects 0 0 0 3
Projects Completed 0 0 0 0
Change Orders 0 0 0 0
Projects Requiring liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0
ESTIMATED SCHEDULE OF PROJECT
Begin Construction March 2022
Complete Construction August 2023
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
Fund
FY 2022
FY 2023
Future Years
Street and Transportation (A) Fund (2017 General Obligation Bond...