Title: Authorize a construction services contract for the Warranted Traffic Signal Installation Group 10, for traffic signal construction at the following four locations: North Bagley Street at West Davis Street; South Great Trinity Forest Way at North Murdeaux Lane; Scyene Road at Scyene Circle; and South Lancaster Road at Wagon Wheels Trails - Select Maintenance, LLC, lowest responsible bidder of three - Not to exceed $1,096,945.60 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds)
Indexes: 5, 6, 8
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: October 27, 2021
COUNCIL DISTRICT(S): 5, 6, 8
DEPARTMENT: Department of Transportation
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the Warranted Traffic Signal Installation Group 10, for traffic signal construction at the following four locations: North Bagley Street at West Davis Street; South Great Trinity Forest Way at North Murdeaux Lane; Scyene Road at Scyene Circle; and South Lancaster Road at Wagon Wheels Trails - Select Maintenance, LLC, lowest responsible bidder of three - Not to exceed $1,096,945.60 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds)

Body
BACKGROUND

This action will authorize a construction contract with Select Maintenance, LLC, lowest responsible bidder of three, to construct four traffic signals as part of services for the Warranted Traffic Signal Installations - Group 10 Project.

Bid specifications were developed and publicly advertised on June 9, 2021 and June 16, 2021, for competitive bids associated with the Warranted Traffic Signal Installations - Group 10 Project. Bids were opened on July 16, 2021.

The following chart illustrates Select Maintenance, LLC's contractual activities with the City of Dallas for the past three years:

PBW DWU PKR TRN

Current Projects 0 0 0 1
Projects Completed 0 0 0 0
Change Orders 0 0 0 0
Projects Requiring liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0


ESTIMATED SCHEDULE OF PROJECT

Begin Construction March 2022
Complete Construction May 2023

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.

FISCAL INFORMATION

Fund
FY 2022
FY 2023
Future Years
Street and Transportation (A) Fund (2017 General Obligation Bond Funds)
$1,096...

Click here for full text