File #: 21-2012    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 10/12/2021 In control: Office of Bond and Construction Management
On agenda: 11/10/2021 Final action:
Title: Authorize a construction services contract for the construction of Fire Station No. 19 replacement facility located at 5600 East Grand Avenue - Imperial Construction, Inc., best value proposer of six - Not to exceed $4,355,000.00 - Financing: 2020 Certificates of Obligation Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: November 10, 2021
COUNCIL DISTRICT(S):|910|DEPARTMENT: Office of Bond and Construction Management
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the construction of Fire Station No. 19 replacement facility located at 5600 East Grand Avenue - Imperial Construction, Inc., best value proposer of six - Not to exceed $4,355,000.00 - Financing: 2020 Certificates of Obligation Fund

Body
BACKGROUND

A Request for Competitive Sealed Proposal was issued on June 23, 2021, for submittals from qualified contractors for evaluation by a Selection Committee comprised of City staff familiar with design and construction of City facilities. Six competitive sealed proposals were received on July 9, 2021. Following an independent review of each submitted proposal, members of the Selection Committee met to determine a cumulative final ranking order of all proposals submitted. The Committee's recommendation of the Best Value Proposal for this construction contract was submitted by Imperial Construction, Inc.

This action will authorize a construction contract with Imperial Construction, Inc. for the construction of Fire Station No. 19 replacement facility. The facility was severely damaged in June 2019, due to severe weather, which took the station out of service. The scope of work includes replacement of the entire facility with code-mandated upgrades enacted since original construction in 1971, as well as compliance with Americans with Disabilities Act, and includes a new physical training room which was not part of the previous station.

Deferral of this item would delay the project's start and completion date, which will continue to negatively impact response times for the Fire Station No. 19 service area. Fire Station No. 19 provides crucial fire and rescue services to the citize...