Title: Authorize Supplemental Agreement No. 2 to the professional services contract with M. Arthur Gensler Jr. & Associates, Inc. to provide security and technology systems design services for the new Transportation Network Center on the first floor of Garage B at Dallas Love Field - Not to exceed $141,071.00, from $243,000.00 to $384,071.00 - Financing: Aviation Construction Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     December 8, 2021

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Aviation

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize Supplemental Agreement No. 2 to the professional services contract with M. Arthur Gensler Jr. & Associates, Inc. to provide security and technology systems design services for the new Transportation Network Center on the first floor of Garage B at Dallas Love Field - Not to exceed $141,071.00, from $243,000.00 to $384,071.00 - Financing:  Aviation Construction Fund

 

Body

BACKGROUND

 

Garage A was built in 1984 and currently offers parking for 3,000 vehicles. Garage B and the Pedestrian Concourse were completed in 2004; Garage B currently provides 4,000 parking spaces.  In 2014, in order to relieve congestion on the lower level curbside at Dallas Love Field, the design team reviewed multiple locations to relocate the Transportation Network Center (TNC) Pick Up area.  Having prepared multiple options for both Garage A and Garage B, it was determined that due to the ability of Garage B to meet and then flex with the potential demand, and the ease at which the solution could be implemented made the Garage B solution more desirable.

 

This action will authorize Supplemental Agreement No. 2 to the professional services contract with M. Arthur Gensler Jr. & Associates, Inc. to provide Security and Technology systems design services for the new TNC on the first floor of Garage B at Dallas Love Field.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                     May 2019

Complete Design                     March 2022

Begin Construction                     August 2023

Complete Construction                     February 2023

 

 

 

 

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On April 10, 2019, City Council authorized a professional services contract with M. Arthur Gensler Jr. & Associates, Inc. to provide architectural and engineering design and construction administration services for the new Transportation Network Center on the first floor of Garage A at Dallas Love Field by Resolution No. 19-0488.

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Aviation Construction Fund

$141,071.00

$0.00

$0.00

 

Original Contract                                                                                                                              $195,000.00

Supplemental Agreement No. 1                                                                                    $  48,000.00

Supplemental Agreement No. 2 (this action)                                          $141,071.00

 

Total                                                                                                                                                                        $384,071.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$141,071.00

Architecture & Engineering

25.66%*

65.48%

$92,371.00

*This item reflects previous Business Inclusion and Development Policy M/WBE goal.

This contract meets the M/WBE goal.

Supplemental Agreement No. 2 - 65.29% Overall M/WBE Participation

M. Arthur Gensler Jr. & Associates, Inc. - Local; Workforce - 95.69% Local

 

OWNER

 

M. Arthur Gensler Jr. & Associates, Inc.

5005 Greenville Avenue

Dallas, Texas 75206

 

Cindy Simpson, Managing Director and Principal

 