File #: 21-2114    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 10/22/2021 In control: Department of Public Works
On agenda: 12/8/2021 Final action:
Title: Authorize the rejection of bids for a twenty-four-month construction services contract for the 2021 sidewalk and barrier free ramp installation paving services improvements project; and the re-advertisements for new bids - Financing: No cost consideration to the City
Indexes: 100
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     December 8, 2021

COUNCIL DISTRICT(S):                     All

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

title

Authorize the rejection of bids for a twenty-four-month construction services contract for the 2021 sidewalk and barrier free ramp installation paving services improvements project; and the re-advertisements for new bids - Financing: No cost consideration to the City

 

body

BACKGROUND

 

This action will authorize the rejection of the bids received for the 2021 Sidewalk and Barrier Free Ramp Improvements at Various Locations Contract due to the unbalanced value of several bid items (See North Central Texas Council of Governments 4th Edition, item 102.12. Disqualification of Bidders). Ragle, Inc., submitted the lowest bid on Friday, September 3, 2021 in the amount of $4,954,266.75 and several bid items were 30-50 percent higher than the original estimates. The Sidewalk Program will re-advertise for new bids and anticipates bringing the construction contract to Council for approval consideration at the February 23, 2022 Council Meeting.

 

This project was publicly advertised for three consecutive weeks on August 11, 2021, August 18, 2021, and August 25, 2021 for the 2021 Sidewalk and Barrier Free Ramp Improvements at Various Locations Contract that includes water and wastewater adjustments at various locations throughout the City. Four sealed bids were received and opened on Friday, September 3, 2021.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     March 2022

Complete Construction                     March 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

 

FISCAL INFORMATION

 

No cost consideration to the City.

 