SUBJECT
title
Authorize a liquidation of the Bid Bond from the construction services contract with C. Green Scaping, LP, in the amount of $46,629.40, for the construction of the Kidd Springs Park Japanese Garden renovations located at 700 West Canty Street - Revenue: Miscellaneous Revenue Fund $46,629.40 (for forfeiture of Bid Bond)
body
BACKGROUND
This action will authorize a liquidation of the Bid Bond for construction of Kidd Springs Park Japanese Garden renovations by C. Green Scaping, LP and will result in revenue in an amount of $46,629.40 which is 5 percent of the total contract (total amount of $932,588.00).
It has been determined to liquidate the Bid Bond from the construction services contract with C. Green Scaping, LP, due to lack of workforce for the construction of the project.
On May 5, 2021 and May 12, 2021, the City of Dallas advertised for bids for Kidd Springs Park Japanese Garden renovations. In response to the advertisement, the Office of Procurement Services received bids from three responsive firms on June 18, 2021.
The scope of work includes the construction of an accessible walkway through the Japanese Garden between the recreation center and creative playground.
The following chart illustrates C. Green Scaping, LP's, contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TRN
Projects Completed |9 9 9||9 9||9 10|Active Projects |9 9 9||99||9 10|Change Orders |9 9 9||99||9 10|Projects Requiring Liquidated Damages |9 9 9||9 9||9 10|Projects Completed by Bonding Company |9 9 9||9 9||9 10|
ESTIMATED SCHEDULE OF PROJECT
Began Design April 2020
Completed Design April 2021
Begin Construction March 2022
Complete Construction August 2022