File #: 22-639    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 3/1/2022 In control: Department of Convention and Event Services
On agenda: 5/25/2022 Final action:
Title: Authorize a decrease in the construction services Contract No. CCT-2020-00013016 with Sawyers Construction, Inc., for Change Order No. 2 reducing the contractor's scope of work for the Kay Bailey Hutchison Convention Center Dallas Elevator and Escalator Modernization project located at 650 South Griffin Street - Not to exceed ($408,655.02) from $6,503,498.00 to $6,094,842.98 - Financing Convention Center Construction Fund
Indexes: 2
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life, Arts & Culture
AGENDA DATE: May 25, 2022
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Convention and Event Services
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a decrease in the construction services Contract No. CCT-2020-00013016 with Sawyers Construction, Inc., for Change Order No. 2 reducing the contractor's scope of work for the Kay Bailey Hutchison Convention Center Dallas Elevator and Escalator Modernization project located at 650 South Griffin Street - Not to exceed ($408,655.02) from $6,503,498.00 to $6,094,842.98 - Financing Convention Center Construction Fund

Body
BACKGROUND

City of Dallas Convention and Event Services department are committed to a new masterplan for the Kay Bailey Hutchison Convention Center Dallas. The Capital Construction Project Management team has been requested to scale back projects to reduce overall capital costs and focus on improvements necessary to maintain the facilities current operations.

This action will decrease the scope of work authorized in the original contract with Sawyers Construction, Inc. The decrease to the contractor's scope of work included with this action is the work associated with removing escalators Nos. 5 and 6, the filling in of the exhibit level floor, the wall and storefront modifications at A/B parking garage level below including masonry infill and flooring, and also the work associated with escalators Nos. 23 and 24 including cutting a new doorway from the top of the escalator landing into the exhibit level pre-function area and the masonry infill of the existing bi-parting door into the Exhibit Hall B from the same escalator landing.

ESTIMATED SCHEDULE OF PROJECT

Began Design June 2020
Completed Design November 2020
Began Construction March 2021
Complete Construction August 2023



PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On November 8, 2017, City Council a...

Click here for full text