STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: May 25, 2022
COUNCIL DISTRICT(S): 14
DEPARTMENT: Department of Transportation
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT
Title
Authorize a construction contract for the Dallas Union Bikeway Connector Project from Houston Street and Nowitzki Way to the intersection of Harwood Street and Woodall Rodgers Freeway access road - Gibson & Associates, Inc., lowest responsible bidder of two - Not to exceed $1,015,842.45 - Financing: Texas Department of Transportation Grant Fund ($554,682.00), Bike Lane Fund ($461,160.45)
Body
BACKGROUND
This action will authorize a construction contract with Gibson & Associates, Inc., lowest responsible bidder of two, to provide construction services for Dallas Union Bikeway Connector Project from Houston Street and Nowitzki Way to the intersection of Harwood Street and Woodall Rodgers Freeway access road.
This project provides for the construction services needed for bicycle and pedestrian improvements. On December 13, 2017, City Council adopted the Downtown Dallas 360 Plan Update. This plan included a list of streets with proposed bicycle and pedestrian improvements in downtown and the surrounding neighborhoods. The list covers the streets affected by this project.
The Dallas Union Bikeway Connector Project will include construction of pavement markings, concrete sidewalks, barrier free ramps, street signage, traffic signal modification and other miscellaneous items necessary to complete the project, in accordance with the plans and specifications
The following chart illustrates Gibson & Associates, Inc.'s contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TWM
Projects Completed|9 9 9 9 10|Change Orders|99 9 9 10|Projects Requiring Liquidated Damages|9 9 9 9 10|Projects Completed by Bonding Company|9 9 9 9 10|
ESTIMATED SCHEDULE OF PROJECT
Begin construction J...