File #: 22-394    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 1/20/2022 In control: Water Utilities Department
On agenda: 5/25/2022 Final action:
Title: Authorize a construction services contract for the installation and rehabilitation of water and wastewater mains and appurtenances at 13 locations (list attached to the Agenda Information Sheet) - Douglas Dailey Construction, LLC, lowest responsible bidder of four - Not to exceed $13,921,735.00 - Financing: Water (Drinking Water) - TWDB 2020 Fund ($8,678,086.34), Wastewater (Clean Water) - TWDB 2021 Fund ($4,000,900.57), Water (Drinking Water) - TWDB 2021 Fund ($1,242,748.09)
Indexes: 1, 13, 2, 4, 6, 7
Attachments: 1. Maps, 2. List, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     May 25, 2022

COUNCIL DISTRICT(S):                     1, 2, 4, 6, 7, 13

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Kimberly Bizor Tolbert

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the installation and rehabilitation of water and wastewater mains and appurtenances at 13 locations (list attached to the Agenda Information Sheet) - Douglas Dailey Construction, LLC, lowest responsible bidder of four - Not to exceed $13,921,735.00 - Financing: Water (Drinking Water) - TWDB 2020 Fund ($8,678,086.34), Wastewater (Clean Water) - TWDB 2021 Fund ($4,000,900.57), Water (Drinking Water) - TWDB 2021 Fund ($1,242,748.09)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with Douglas Dailey Construction, LLC for the installation and rehabilitation of approximately 27,884 feet of water and wastewater mains. This includes the installation of approximately 1,150 feet of 6-inch, 5,690 feet of 8-inch, 9,634 feet of 12-inch, 90 feet of 16-inch, and 2,500 feet of 20-inch diameter water mains. It also includes the installation of approximately 10 feet of 6-inch, 3,410 feet of 8-inch, 1,070 feet of 12-inch, and 1,800 feet of 18-inch diameter wastewater mains and the rehabilitation of approximately 450 feet of 10-inch, 570 feet of 15-inch, 1,130 feet of 18-inch, and 380 feet of 24-inch diameter wastewater mains.

 

The existing water and wastewater mains targeted for replacement and rehabilitation were built between 1906 and 1977. The existing water and wastewater mains have reached the end of their useful life and are in need of rehabilitation or replacement due to poor condition, service interruptions and increased maintenance efforts. In addition, some of these mains need to be upsized to meet future demands. The installation of the proposed segments will improve the capacity of the water and wastewater systems, reduce maintenance costs, and minimize service interruptions.

 

The following chart illustrates Douglas Dailey Construction, LLC’s contractual activities with the City of Dallas for the past three years:

 

 

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     0                     0                     0                     0

Active Projects                     0                     2                     0                     0

Change Orders                     0                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     June 2022

Complete Construction                     December 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This action has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Water (Drinking Water) - TWDB 2020 Fund

$8,678,086.34

$0.00

$0.00

Wastewater (Clean Water) - TWDB 2021 Fund

$4,000,900.57

$0.00

$0.00

Water (Drinking Water) - TWDB 2021 Fund

$1,242,748.09

$0.00

$0.00

Total

$13,921,735.00

$0.00

$0.00

 

                     Council District                     Amount

 

                     1                     $  4,215,107.40

                     2                     $  1,113,179.71

                     4                     $     711,836.00

                     6                     $  6,225,819.47

                     7                     $     981,894.39

                     13                     $     673,898.03

 

                     Total                     $13,921,735.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$13,921,735.00

Construction

32.00%

34.00%

$4,733,389.00

This contract exceeds the M/WBE goal.

Douglas Dailey Construction, LLC- Non-local; Workforce - 22.85% Local

 

PROCUREMENT INFORMATION

 

The following four bids with quotes were opened on February 18, 2022:

 

*Denotes successful bidder

 

Bidders                     Bid Amount

 

*Douglas Dailey Construction, LLC                      $13,921,735.00

 2005 Bluff Springs Road

 Ferris, TX 75125

SYB Construction Co. Inc.                     $16,544,922.00

Camino Construction LP                     $16,583,483.50

John Burns Construction Company of Texas, Inc.                      $18,611,243.00

 

OWNER

 

Douglas Dailey Construction, LLC

 

Douglas Dailey, President

 

MAPS

 

Attached