File #: 22-1217    Version: 1 Name:
Type: ITEMS FOR INDIVIDUAL CONSIDERATION Status: Approved
File created: 5/12/2022 In control: Park & Recreation Department
On agenda: 5/25/2022 Final action:
Title: Authorize an increase to the construction services contract with J.C. Commercial Inc. for Change Order No. 15 for additional work at the Willie B. Johnson Recreation Center in Hamilton Park, located at 12225 Willowdell Drive - Not to exceed $560,431.54, from $8,010,089.79 to $8,570,521.33 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund)
Indexes: 10
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life, Arts & Culture
AGENDA DATE: May 25, 2022
COUNCIL DISTRICT(S): 10
DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT

Title
Authorize an increase to the construction services contract with J.C. Commercial Inc. for Change Order No. 15 for additional work at the Willie B. Johnson Recreation Center in Hamilton Park, located at 12225 Willowdell Drive - Not to exceed $560,431.54, from $8,010,089.79 to $8,570,521.33 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund)

Body
BACKGROUND

This action will authorize Change Order No. 15 to the construction services contract with J.C. Commercial, Inc. The original scope of work was for the addition of a new senior activity center, new technology center, a new gymnasium, and the expansion of the existing parking lot.

The project scope addressed with this change order is necessary to: a) comply with building code upgrades to the original Recreation Center facility, b) address the revised work scope caused by the franchise electric utility company's (Oncor) decision to provide power to the site via underground power delivery in lieu of the planned aerial delivery, causing revisions to planned site features of the project due to a required power easement provision for the utility franchise company, c) address work scope to address 2021 Winter Storm Uri damages to existing interior space(s) and finishes as well as to address damaged domestic water supply lines in the original recreation center building, and d) address additional unforeseen work items.

Change Order No. 15 results in an increase of $560,431.54, increasing the contract amount from $8,010,089.79 to $8,570,521.33.

ESTIMATED SCHEDULE OF PROJECT

Began Construction April 2020
Complete Construction November 2022


PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On December 12, 2019, the Park and R...