Dallas Logo
File #: 22-1154    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 5/6/2022 In control: Department of Public Works
On agenda: 6/22/2022 Final action:
Title: Authorize a construction services contract for the construction of Street Reconstruction Group 17-3003 (list attached to the Agenda Information Sheet) - David Bowers dba HD Way Concrete Service, LLC, lowest responsible bidder of six - Not to exceed $4,015,910.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($2,597,815.00) Water Capital Improvement F Fund ($669,283.00), Water Construction Fund ($29,650.00), Wastewater Capital Improvement G Fund ($689,762.00), and Wastewater Construction Fund ($29,400.00)
Indexes: 3
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     June 22, 2022

COUNCIL DISTRICT(S):                     3

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the construction of Street Reconstruction Group 17-3003 (list attached to the Agenda Information Sheet) - David Bowers dba HD Way Concrete Service, LLC, lowest responsible bidder of six - Not to exceed $4,015,910.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($2,597,815.00) Water Capital Improvement F Fund ($669,283.00), Water Construction Fund ($29,650.00), Wastewater Capital Improvement G Fund ($689,762.00), and Wastewater Construction Fund ($29,400.00)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with David Bowers dba HD Way Concrete Service, LLC for the construction of two local street reconstruction projects as Street Reconstruction Group 17-3003.

 

The street reconstruction projects will include replacing the existing deteriorating concrete streets with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, replacement of the drainage system, and water and wastewater improvements.

 

David Bowers dba HD Way Concrete Service, LLC is a Grand Prairie-based corporation, operating within the corporate city limits of Grand Prairie, Texas.

 

Following are the locations and construction costs for each project:

 

Project                     Council District                     Amount

 

Dove Creek Way from Myrtlewood Drive

to Swansee Street                     3                        $2,979,840.00

 

Grassy Ridge Trail from Penguin Drive

to Scottsboro Lane                     3                     $1,036,070.00

 

The following chart illustrates David Bowers dba HD Way Concrete Service, LLC’s contractual activities with the City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     0                     0                     0                     0

Active Projects                     0                     0                     0                     0

Change Orders                     0                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

If this project group is not awarded for construction at this time, the streets will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicles utilizing the street. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     August 2022

Complete Construction                     December 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Funds)

$2,597,815.00

$0.00

$0.00

Water Capital Improvement F Fund

$   669,283.00

$0.00

$0.00

Water Construction Fund

$     29,650.00

$0.00

$0.00

Wastewater Capital Improvement G Fund

$   689,762.00

$0.00

$0.00

Wastewater Construction Fund

$     29,400.00

$0.00

$0.00

Total

$4,015,910.00

$0.00

$0.00

 

 

 

 

 

 

 

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$4,015,910.00

Construction

32.00%

35.00%

$1,405,568.50

This contract exceeds the M/WBE goal.

David Bowers dba HD Way Concrete Service LLC - Local; Workforce - 67.00% Local

 

PROCUREMENT INFORMATION

 

The following six bids were received and opened on April 8, 2022:

 

*Denotes successful bidder

 

Bidders                                                                                                                               Bid Amount

 

 *David Bowers dba

   HD Way Concrete Service, LLC                                           $4,015,910.00

  2760 Autumn Breeze

  Grand Prairie, TX 75052

Jeske Construction Company                                                                $4,172,194.00

Camino Construction, L.P.                                                                                     $4,199,210.00

Tiseo Paving Company                                                                                     $5,114,498.25

DDM Construction Corporation                                                                $5,170,760.04

SYB Construction CO., Inc.                                                                $6,312,538.00

 

OWNER

 

David Bowers dba HD Way Concrete Service, LLC

 

David W. Bowers, President

 

MAP

 

Attached