Title: Authorize a construction services contract for the construction of Bonnie View Road from Ann Arbor Avenue to Cummings Street - Camino Construction, LP, lowest responsible bidder of seven - Not to exceed $2,503,547.50 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($2,165,922.50), Water Capital Improvement F Fund ($212,248.00), Water Construction Fund ($3,300.00), Wastewater Capital Improvement G Fund ($119,977.00), and Wastewater Construction Fund ($2,100.00)
Indexes: 4
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     June 22, 2022

COUNCIL DISTRICT(S):                     4

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

Title

 

Authorize a construction services contract for the construction of Bonnie View Road from Ann Arbor Avenue to Cummings Street - Camino Construction, LP, lowest responsible bidder of seven - Not to exceed $2,503,547.50 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($2,165,922.50), Water Capital Improvement F Fund ($212,248.00), Water Construction Fund ($3,300.00), Wastewater Capital Improvement G Fund ($119,977.00), and Wastewater Construction Fund ($2,100.00)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with Camino Construction, LP for the construction of Bonnie View Road from Ann Arbor Avenue to Cummings Street. The project was funded in the 2017 Bond Program under the street reconstruction category. The scope consists of replacing the existing street pavement that is in deteriorating condition with new 40’ wide, 9-inch thick, reinforced concrete pavement with curb and gutter. Also, it includes driveway approaches, sidewalks, drainage improvement, water and wastewater improvements, and other miscellaneous items necessary to complete the project.

 

Camino Construction, LP is Lewisville-based corporation, and is a registered vendor with the City of Dallas.

 

The following chart illustrates Camino Construction, LP’s contractual activities with the

City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     2                     1                     0                     0

Active Projects                     2                     0                     0                     0

Change Orders                     0                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                                    0                     0                     0

 

If this project is not awarded for construction at this time, the street will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicles utilizing the street. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          August 2022

Complete Construction                     July 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

$2,165,922.50

$0.00

$0.00

Water Capital Improvement F Fund

$   212,248.00

$0.00

$0.00

Water Construction Fund

$       3,300.00

$0.00

$0.00

Wastewater Capital Improvement G Fund

$   119,977.00

$0.00

$0.00

Wastewater Construction Fund

$       2,100.00

$0.00

$0.00

Total

$2,503,547.50

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$2,503,547.50

Construction

32.00%

34.49%

$863,500.00

This contract exceeds the M/WBE goal.

Camino Construction LP - Non-local; Workforce - 75.00% Local

 

 

 

 

 

PROCUREMENT INFORMATION

 

The following seven bids were received and opened on April 15, 2022:

 

*Denotes successful bidder

 

Bidders                                                                                                                               Bid Amount

 

* Camino Construction, LP                                                                $2,503,547.50

  1208 Metro Park Blvd

  Lewisville, Texas 75057

Estrada Concrete Company                                                                $2,630,037.00

Jeske Construction Company                                                                $2,718,288.15

Texas Standard Construction                                                                $2,754,552.75

XIT Paving and Construction                                                                $3,181,875.00

Tiseo Paving Company                                                                                     $3,325,061.00

DDM Construction Corporation                                                                $4,190,255.00

 