STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: June 22, 2022
COUNCIL DISTRICT(S): 13
DEPARTMENT: Office of Bond and Construction Management
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT
title
Authorize (1) rescinding the construction contract awarded to Post L Group, LLC, previously approved on November 10, 2021 by Resolution No. 21-1850, for the construction of Fire Station No. 41 Replacement facility; and (2) to re-advertise this project located at 5920 Royal Lane - Financing: No cost consideration to the City
body
BACKGROUND
On November 10, 2021, City Council authorized a construction contract for the construction of the Fire Station No. 41 replacement facility, located at 5920 Royal Lane to Post L Group, LLC, best value proposer of eight in the amount not to exceed $4,458,098.00.
It is now desirable to rescind the construction contract awarded with Post L Group, LLC as it is unable to perform the construction work under the amount awarded. Therefore, the City will re-advertise this project.
ESTIMATED SCHEDULE OF PROJECT
Re-advertise July 2022
Award Construction August/September 2022
Begin Construction October/November 2022
Complete Construction October/November 2023
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On August 26, 2020, City Council authorized a professional services contract with PGAL Architects, Inc., to provide design and construction administration services of Fire Station No. 41 located at 5920 Royal Lane by Resolution 20-1260.
On November 10, 2021, City Council authorized a construction contract with Post L Group, LLC for construction services for Fire Station 41 Replacement facility by Resolution 21-1850.
FISCAL INFORMATION
Financing: No cost consideration to the City.
MAP
Attached