File #: 22-1481    Version: 1 Name:
Type: ITEMS FOR INDIVIDUAL CONSIDERATION Status: Approved
File created: 6/16/2022 In control: Office of Bond and Construction Management
On agenda: 6/22/2022 Final action:
Title: Authorize (1) rescinding the construction contract awarded to Post L Group, LLC, previously approved on November 10, 2021 by Resolution No. 21-1850, for the construction of Fire Station No. 41 Replacement facility; and (2) to re-advertise this project located at 5920 Royal Lane - Financing: No cost consideration to the City
Indexes: 13
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     June 22, 2022

COUNCIL DISTRICT(S):                     13

DEPARTMENT:                     Office of Bond and Construction Management

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

title

Authorize (1) rescinding the construction contract awarded to Post L Group, LLC, previously approved on November 10, 2021 by Resolution No. 21-1850, for the construction of Fire Station No. 41 Replacement facility; and (2) to re-advertise this project located at 5920 Royal Lane - Financing: No cost consideration to the City

 

body

BACKGROUND

 

On November 10, 2021, City Council authorized a construction contract for the construction of the Fire Station No. 41 replacement facility, located at 5920 Royal Lane to Post L Group, LLC, best value proposer of eight in the amount not to exceed $4,458,098.00.

 

It is now desirable to rescind the construction contract awarded with Post L Group, LLC as it is unable to perform the construction work under the amount awarded. Therefore, the City will re-advertise this project.

 

ESTIMATED SCHEDULE OF PROJECT

 

Re-advertise                     July 2022

Award Construction                     August/September 2022

Begin Construction                     October/November 2022

Complete Construction                     October/November 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On August 26, 2020, City Council authorized a professional services contract with PGAL Architects, Inc., to provide design and construction administration services of Fire Station No. 41 located at 5920 Royal Lane by Resolution 20-1260.

 

On November 10, 2021, City Council authorized a construction contract with Post L Group, LLC for construction services for Fire Station 41 Replacement facility by Resolution 21-1850.

 

FISCAL INFORMATION

 

Financing: No cost consideration to the City.

 

MAP

 

Attached