Title: Authorize (1) the rejection of bids for a construction services contract for the Street Reconstruction Group 17-1410 (list attached to the Agenda Information Sheet); and (2) the re-advertisements for new bids - Financing: No cost consideration to the City
Indexes: 14
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 14, 2022

COUNCIL DISTRICT(S):                     14

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

Title

Authorize (1) the rejection of bids for a construction services contract for the Street Reconstruction Group 17-1410 (list attached to the Agenda Information Sheet); and (2) the re-advertisements for new bids - Financing: No cost consideration to the City

 

Body

BACKGROUND

 

This action will authorize the rejection of the one bid received for the Street Reconstruction Group 17-1410, due to the bid received being 55 percent higher than the Engineer’s estimate. Estrada Concrete Company, LLC, submitted the only bid received on Friday, July 15, 2022, in the amount of $3,732,407.70. Street Reconstruction Group 17-1410 is anticipated to be re-advertised for a new round of competitive bids and bring the construction services contract to City Council for consideration at the January 26, 2023, City Council meeting.

 

This project was publicly advertised for two consecutive weeks on June 29, 2022 and July 6, 2022 for the Street Reconstruction Group 17-1410. One sealed bid was received and opened on Friday, July 15, 2022.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     May 2023

Complete Construction                     April 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

No cost consideration to the City.

 

MAPS

 

Attached