Dallas Logo
File #: 22-1784    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/9/2022 In control: Department of Public Works
On agenda: 9/14/2022 Final action:
Title: Authorize (1) the rejection of one bid received for construction services contract for the Jefferson-Twelfth Connector Lane Diet/Removal Project; and (2) the re-advertisement for new bids - Financing: No cost consideration to the City
Indexes: 1
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 14, 2022

COUNCIL DISTRICT(S):                     1

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

title

Authorize (1) the rejection of one bid received for construction services contract for the Jefferson-Twelfth Connector Lane Diet/Removal Project; and (2) the re-advertisement for new bids - Financing: No cost consideration to the City

 

body

BACKGROUND

 

This action will authorize the rejection of one bid received for the Jefferson/Twelfth Connector Lane Diet/Removal Project due to the only bid far exceeding the project budget and engineer’s estimate.  Rebcon, LLC, submitted the only bid received on Friday, June 10, 2022, in the amount of $5,923,355.00 for the base bid and $6,987,232.00 total of base bid plus additive alternate bids. This exceeds the engineer’s estimate of $2,750,000.00 with several bid items being over 50 percent or higher than the engineer’s estimate.  The Jefferson/Twelfth Connector Project is anticipated to be readvertised for a new round of competitive bids and bring the construction project to Council for consideration at the December 14, 2022, City Council meeting. 

 

This project was publicly advertised for three consecutive weeks on May 25, 2022, June 1, 2022, and June 8, 2022, for the Jefferson/Twelfth Connector Lane Diet/Removal Project.  One sealed bid was received on Friday, June 10, 2022.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     April 2023

Complete Construction                     April 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

 

FISCAL INFORMATION

 

No cost consideration to the City.

 