Dallas Logo
File #: 22-1544    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/6/2022 In control: Department of Public Works
On agenda: 9/28/2022 Final action:
Title: Authorize a construction services contract for the construction of Alley Reconstruction Group 17-4002 (list attached to the Agenda Information sheet) - HD Way Concrete Service LLC, lowest responsible bidder of four - Not to exceed $1,653,450.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($1,247,560.00), Wastewater Capital Improvement G Fund ($400,590.00), and Wastewater Construction Fund ($5,300.00)
Indexes: 4
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 28, 2022

COUNCIL DISTRICT(S):                     4

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the construction of Alley Reconstruction Group 17-4002 (list attached to the Agenda Information sheet) - HD Way Concrete Service LLC, lowest responsible bidder of four - Not to exceed $1,653,450.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($1,247,560.00), Wastewater Capital Improvement G Fund ($400,590.00), and Wastewater Construction Fund ($5,300.00)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with HD Way Concrete Service LLC for the construction of four alley reconstruction projects as Alley Reconstruction Group 17-4002.

 

The scope of the project group will include construction of reinforced concrete pavement, storm sewer, wastewater main improvements and other miscellaneous items necessary to complete these projects, in accordance with the intent of the plans and specifications. 

 

Following are the locations and construction costs for each project:

 

Project                                                                                                         Council District                                                               Amount

 

Dugald Place (2104-2336) and                                                                4                                                                                    $343,520.00

East Illinois Avenue (2005-2249)

 

Deer Path Drive (2211-2323) and                                                               4                                                                                    $800,135.00

Kellogg Avenue (2905-3311)

 

East Ledbetter Drive (3163-3241) and                                          4                                                                                    $236,180.00

Dahlia Drive (3132-3244)

 

Bonnie View Road (4307-4435) and                                          4                                                                                    $273,615.00

Cicero Street (4302-4446)

 

 

 

HD Way Concrete Service LLC is a Grand Prairie - based corporation, and is a registered vendor with the City of Dallas.   HD Way Concrete Service LLC has had no contractual activities with the City of Dallas within the past three years.

 

If this project group is not awarded for construction at this time, the alleys will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the city and potential damages to vehicles utilizing the alleys. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          December 2022

Complete Construction                     July 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Street and Transportation (A) Fund (2017 General Obligation Funds)

$1,247,560.00

$0.00

$0.00

Wastewater Capital Improvement G Fund

$   400,590.00

$0.00

$0.00

Wastewater Construction Fund

$       5,300.00

$0.00

$0.00

Total

$1,653,450.00

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$1,653,450.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

32.00%

32.00%

$529,104.00

This contract meets the M/WBE goal.

•  HD Way Concrete Service, LLC- Local; Workforce - 67.00% Local

 

 

PROCUREMENT INFORMATION

 

The following four bids were received and opened on June 24, 2022:

 

*Denotes successful bidder

 

Bidders                                                                                                                                                   Bid Amount

 

*HD Way Concrete Service LLC                                                                                    $1,653,450.00

 2760 Autumn Breeze

 Grand Prairie, Texas 75052                                                                                    

Camino Construction, LP                                                                                                         $1,986,160.00

Urban Infraconstruction                                                                                                         $1,997,405.00

Estrada Concrete Company, LLC                                                                                    $2,011,824.00

 

OWNER

 

HD Way Concrete Service LLC

 

David Bowers, President

 

MAPS

 