File #: 22-1930    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/19/2022 In control: Department of Public Works
On agenda: 9/28/2022 Final action:
Title: Authorize acquisition from Computer Science Innovations LLC Series 12, of approximately 7,158 square feet of land improved with a manufactured dwelling located in Van Zandt County for the Lake Tawakoni 144-inch Transmission Pipeline Project - Not to exceed $78,000.00 ($75,000.00, plus closing costs and title expenses not to exceed $3,000.00) - Financing: Water Construction Fund
Indexes: 200
Attachments: 1. Map, 2. Resolution, 3. Exhibit A, 4. Exhibit B
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 28, 2022

COUNCIL DISTRICT(S):                     Outside City Limits

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

title

Authorize acquisition from Computer Science Innovations LLC Series 12, of approximately 7,158 square feet of land improved with a manufactured dwelling located in Van Zandt County for the Lake Tawakoni 144-inch Transmission Pipeline Project - Not to exceed $78,000.00 ($75,000.00, plus closing costs and title expenses not to exceed $3,000.00) - Financing: Water Construction Fund

 

body

BACKGROUND

 

This item authorizes the acquisition from Computer Science Innovations LLC Series 12, of approximately 7,158 square feet of land located in Van Zandt County. This property will be used for the construction of a 144-inch raw water transmission line for the Lake Tawakoni 144-inch Transmission Pipeline Project. The consideration is based on an independent appraisal. There are no relocation benefits associated.

 

This acquisition is part of the right-of-way required to construct approximately 32 miles of pipeline from Lake Tawakoni to the Interim Balancing Reservoir located in Terrell, Texas; and then to the Eastside Water Treatment Plant located in Sunnyvale, Texas. The new raw water pipeline will augment the existing 72-inch and 84-inch pipelines. The construction of this pipeline will give Dallas Water Utilities the ability to utilize the full capacity of both the Lake Tawakoni and the Lake Fork raw water supply to meet the current city needs and future water demands.

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Water Construction Fund

$78,000.00

$0.00

$0.00

 

 

OWNER

 

Computer Science Innovations LLC Series 12

 

Scott Streit, Manager

 