STRATEGIC PRIORITY: Quality of Life, Arts & Culture
AGENDA DATE: November 9, 2022
COUNCIL DISTRICT(S): 2, 6
DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with RoeschCo Construction, Inc. for additional work on the Trinity Strand Trail Phase 2, located between Inwood Road Dallas Area Rapid Transit Station to Turtle Creek Boulevard - Not to exceed $851,117.52, increasing the contract amount from $5,521,648.56 to $6,372,766.08 - Financing: Street and Transportation Improvement Funds (2012 General Obligation Bond Fund)
Body
BACKGROUND
This action will authorize Change Order No. 2 to the construction services contract with RoeschCo Construction, Inc. The original scope of work was for the construction of the Trinity Strand Trail Phase 2.
The project scope addressed with this change order is necessary to add traffic signal lights to comply with requests from the Transportation Department and address additional unforeseen work items.
Change Order No. 2 adds 66 working days to the contract time. This change results in an increase of $851,117.52, increasing the contract amount from $5,521,648.56 to $6,372,766.08.
ESTIMATED SCHEDULE OF PROJECT
Began Construction April 2021
Complete Construction March 2023
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On October 1, 2020, the Park and Recreation Board authorized a contract with RoeschCo Construction, Inc. for the construction the Trinity Strand Trail Phase 2, located between Inwood Road DART Station to Turtle Creek Boulevard.
On October 28, 2020, City Council authorized a construction contract for the construction of the Trinity Strand Trail by Resolution No. 20-1719.
FISCAL INFORMATION
Fund
FY 2023
FY 2024
Future Years
Street and Transportation Improvement Funds (2012 General Obligation Bond Funds)
$851,117.52
$0.00
$0.00
Construction Co...