STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: November 9, 2022
COUNCIL DISTRICT(S): 10
DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT
Title
Authorize a construction services contract for the construction of Package B for Street Reconstruction Group 17-10004 and Alley Reconstruction Group 17-10001 (list attached to the Agenda Information Sheet) - Jeske Construction Co., lowest responsible bidder of two - Not to exceed $1,836,990.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($1,604,655.00), Water Capital Improvement (F) Fund ($80,370.00), Water Construction Fund ($3,180.00), Wastewater Capital Improvement (G) Fund ($145,145.00), and Wastewater Construction Fund ($3,640.00)
Body
BACKGROUND
This action will authorize a construction services contract with Jeske Construction Co., for the construction of Package B for Street Reconstruction Group 17-10004 and Alley Reconstruction Group 17-10001.
The project group scope for the Street Reconstruction project at Rolling Rock Lane from Hackney Lane to Fern Hollow Drive will include the construction to replace the existing deteriorating concrete street with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, paving marking, replacement of the drainage system, water and wastewater improvements.
The project group scope for Alley Reconstruction projects at 10106-10160 Caribou Trail and 10127-10143 Ferndale Road and 10163-10199 Vistadale Drive and 10200-10200 Trailcliff Drive will include the construction to replace the existing deteriorating concrete alleys with new reinforced concrete alley pavement, and storm drainage improvements.
Following are the locations and construction costs for each project:
Project Council District Amount
Rolling Rock Lane from Hackney Lane
to Fern Hollow Drive 10 $1,081,385.00
Caribou Trail alley (10106-10160)
and Ferndale Road alley (10127-10143) 10 $ 440,165.00
Vistadale Drive alley (10163-10199)
and Trailcliff Drive alley (10200-10200) 10 $ 315,440.00
Jeske Construction Co. is a Dallas-based corporation, operating within the corporate city limits of Dallas, Texas.
The following chart illustrates Jeske Construction Co.’s, contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TNR
Projects Completed 5 0 1 0
Active Projects 2 0 0 0
Change Orders 5 0 4 0
Projects Requiring Liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0
If this project group is not awarded for construction at this time, the street and alleys will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicle utilizing the roadways. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.
ESTIMATED SCHEDULE OF PROJECT
Begin Construction January 2023
Complete Construction January 2024
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
Fund |
FY 2023 |
FY 2024 |
Future Years |
Street and Transportation (A) Fund (2017 General Obligation Funds) |
$1,604,655.00 |
$0.00 |
$0.00 |
Water Capital Improvement (F) Fund |
$ 80,370.00 |
$0.00 |
$0.00 |
Water Construction Fund |
$ 3,180.00 |
$0.00 |
$0.00 |
Wastewater Capital Improvement (G) Fund |
$ 145,145.00 |
$0.00 |
$0.00 |
Wastewater Construction Fund |
$ 3,640.00 |
$0.00 |
$0.00 |
Total |
$1,836,990.00 |
$0.00 |
$0.00 |
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
$1,836,990.00 |
Construction |
32.00% |
M/WBE Subcontracting % |
M/WBE Overall % |
M/WBE Overall Participation $ |
33.53% |
33.53% |
$616,016.00 |
• This contract exceeds the M/WBE goal. |
• Jeske Construction Company- Local; Workforce - 85.00% Local |
PROCUREMENT INFORMATION
The following two bids were received and opened on August 19, 2022:
*Denotes successful bidder
Bidders Bid Amount
*Jeske Construction Co. $1,836,990.00
2546 Merrell Road, Suite 106
Dallas, Texas 75229
Wavetron Corporation
DBA Wavetron Enterprises **Non-responsive
**Wavetron Corporation, DBA Wavetron Enterprises was disqualified for being non-responsive for failing to submit completed bid documents.
OWNER
Jeske Construction Co.
Steve Jeske, President
MAPS
Attached