Dallas Logo
File #: 23-8    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 11/3/2022 In control: Department of Public Works
On agenda: 1/11/2023 Final action:
Title: Authorize a construction services contract for the Service Maintenance Area 3 - 2023 Improved Alley Maintenance Project (list attached to the Agenda Information Sheet) - Talbran Enterprises, LLC, lowest responsible bidder of four - Not to exceed $630,404.37 - Financing: Street and Alley Improvement Fund (subject to annual appropriation)
Indexes: 13, 14, 2, 6
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: January 11, 2023
COUNCIL DISTRICT(S): 2, 6, 13, 14
DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the Service Maintenance Area 3 - 2023 Improved Alley Maintenance Project (list attached to the Agenda Information Sheet) - Talbran Enterprises, LLC, lowest responsible bidder of four - Not to exceed $630,404.37 - Financing: Street and Alley Improvement Fund (subject to annual appropriation)

Body
BACKGROUND

This action will authorize a construction services contract with Talbran Enterprises, LLC, lowest responsible bidder of four, to provide construction services for the Service Maintenance Area 3 - 2023 Improved Alley Maintenance Project.

The Infrastructure Management Program has, for the last few years, identified a need for maintenance of alleys needing partial reconstruction. Improved alleys are defined as alleys that have been constructed in concrete or asphalt. Beginning in Fiscal Year (FY) 2022, funding had been provided for the maintenance of concrete alleys that are only in need of partial reconstruction, or less than 25% of pavement repair. In FY 2022, this program was completed in house and in FY 2023, the Department of Public Works went through the bidding process to procure four separate contracts, one for each quadrant of the city, with the intention of making the contract more attractive to the smaller Minority and Women-owned Business Enterprises (M/WBE) contractors.

Following are the locations and construction costs for each project:

Project Council District Amount

Langdon Avenue (2301-2427)|99|$90,057.76
and (2302-2426) West Lovers Lane

Langdon Avenue (2302-2426)
and Roanoke Avenue (2303-2427)|99|$90,057.76

Langdon Avenue (2115-2151)
and West Lovers Lane (2118-2154)|99|$90,057.77

High Mesa Drive (3505-3659)|99|$90,057.77
...