Dallas Logo
File #: 23-306    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 1/11/2023 In control: Department of Public Works
On agenda: 3/8/2023 Final action:
Title: Authorize a construction services contract for the construction of Street Reconstruction Group 17-1410 - (list attached to the Agenda Information Sheet) - Estrada Concrete Co., LLC, lowest responsible bidder of four - Not to exceed $3,246,608.20 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($2,963,343.20), Water Capital Improvement F Fund ($162,310.00), Water Construction Fund ($8,700.00), Wastewater Capital Improvement G Fund ($105,505.00), and Wastewater Construction Fund ($6,750.00)
Indexes: 14
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     March 8, 2023

COUNCIL DISTRICT(S):                     14

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the construction of Street Reconstruction Group 17-1410 - (list attached to the Agenda Information Sheet) - Estrada Concrete Co., LLC, lowest responsible bidder of four - Not to exceed $3,246,608.20 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($2,963,343.20), Water Capital Improvement F Fund ($162,310.00), Water Construction Fund ($8,700.00), Wastewater Capital Improvement G Fund ($105,505.00), and Wastewater Construction Fund ($6,750.00)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with Estrada Concrete Co., LLC, for the construction of three street reconstruction projects as Street Reconstruction Group 17-1410.

 

The scope of the project group will include replacing the existing deteriorating streets with new reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, pavement marking, storm drainage, water and wastewater improvements and other miscellaneous items necessary to complete the project in accordance with the plans and specifications.

 

Estrada Concrete Co., LLC is a Hutchins-based corporation, operating within the corporate city limits of Hutchins, Texas.

 

The following chart illustrates Estrada Concrete Co., LLC’s contractual activities with the City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     6                     0                     0                     0

Active Projects                     15                     2                     0                     0

Change Orders                     3                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                                    0                     0                     0

 

Following are the locations and construction costs for each project:

 

Project                                                                                                         Council District                                          Amount

 

North Munger Boulevard from

Tremont Street to Worth Street                     14                                          $   854,360.50

 

North Munger Boulevard from

Worth Street to Junius Street                                          14                                          $   830,733.70

 

North Munger Boulevard from

Junius Street to Gaston Avenue                                          14                     $1,561,514.00

 

If this project group is not awarded for construction at this time, the streets will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicles utilizing the streets. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     June 2023

Complete Construction                     April 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On September 14, 2022, City Council authorized the rejection of bids for the construction services contract for Street Reconstruction Group 17-1410 and the readvertisement for new bids by Resolution No. 22-1355.

 

FISCAL INFORMATION

 

Fund

FY 2023

FY 2024

Future Years

Street and Transportation (A) Fund (2017 General Obligation Funds)

$2,963,343.20

$0.00

$0.00

Water Capital Improvement F Fund

$   162,310.00

$0.00

$0.00

Water Construction Fund

$       8,700.00

$0.00

$0.00

Wastewater Capital Improvement G Fund

$   105,505.00

$0.00

$0.00

Wastewater Construction Fund

$       6,750.00

$0.00

$0.00

Total

$3,246,608.20

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$3,246,608.20

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

37.00%

100.00%

$3,246,608.20

This contract exceeds the M/WBE goal.

Estrada Concrete Company, LLC - Non-local; Workforce - 67.00% Local

 

PROCUREMENT INFORMATION

 

The following four bids were received and opened on December 16, 2022:

 

*Denotes successful bidder

 

Bidders                                                                                                                                                   Bid Amount

 

*Estrada Concrete Co., LLC                                                                                     $3,246,608.20

  605 Skyline Drive

  Hutchins, TX 75141

Tiseo Paving Company                     $4,439,487.08

Jeske Construction Company                     $4,498,292.00

HD Way Concrete Services, LLC                     **Non-responsive

 

**HD Way Concrete Services, LLC was deemed non-responsive due to an incorrect bid schedule.

 

OWNER

 

Estrada Concrete Co., LLC

 

Francisco Estrada, President

 

MAPS

 

Attached