Title: Authorize Supplemental Agreement No. 2 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway - Not to exceed $2,294,766.00, from $975,809.00 to $3,270,575.00 - Financing: City Hall, City Service, and Maintenance Facilities (2006 General Obligation Bond Fund) ($656,378.44), Park and Recreation Facilities (2006 General Obligation Bond Fund) ($486,636.56), Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund) ($289,187.80), and Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund) ($862,563.20 $1,151,751.00)
Indexes: 10
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life, Arts & Culture

AGENDA DATE:                     April 12, 2023

COUNCIL DISTRICT(S):                     10

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     John D. Jenkins

______________________________________________________________________

SUBJECT

 

Title

Authorize Supplemental Agreement No. 2 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway - Not to exceed $2,294,766.00, from $975,809.00 to $3,270,575.00 - Financing:  City Hall, City Service, and Maintenance Facilities (2006 General Obligation Bond Fund) ($656,378.44), Park and Recreation Facilities (2006 General Obligation Bond Fund) ($486,636.56), Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund) ($289,187.80), and Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund) ($862,563.20 $1,151,751.00)

 

Body

BACKGROUND

 

On June 8, 2022, the City Council authorized a Design-Build services contract to provide pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway to Phoenix I Restoration and Construction, LLC, in an amount not to exceed $975,809.00.

 

This action will authorize Supplemental Agreement No. 2 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for the pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway, increasing the not to exceed contract value from $975,809.00 to $3,270,575.00.  This supplemental agreement will extend the contract time by 133 calendar days.

 

 

 

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                          June 2022

Completed Design                                           February 2023

Began Construction                                          July 2022

Complete Construction                     August 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On April 11, 2023, the Park and Recreation Board will consider Supplemental Agreement No. 2 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway.

FISCAL INFORMATION

 

Fund

FY 2023

FY 2024

Future Years

City Hall, City Service, and Maintenance Facilities (2006 Bond Fund)

$656,378.44

$0.00

$0.00

Park and Recreation Facilities (2006 Bond Fund)

$  486,636.56

$0.00

$0.00

Fair Park (C) Improvements (2017 Bond Fund)

$   289,187.80

$0.00

$0.00

Park and Recreation (B) Facilities (2017 Bond Fund)

$   862,563.20  $1,151,751.00

$0.00

$0.00

Total

$2,294,766.00

$0.00

$0.00

 

Design-Build Contract                                                                                    $   975,809.00

Supplemental Agreement No. 1                                                               $              0.00

Supplemental Agreement No. 2 (this action)                     $2,294,766.00

 

Total                                                                                                         $3,270,575.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

 

 

 

 

Contract Amount

Procurement Category

M/WBE Goal

$2,294,766.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

38.26%

38.26%

$877,969.00

This contract exceeds the M/WBE goal.

Phoenix I Restoration and Construction, LLC - Local; Workforce - 60.89% Local

 

OWNER

 

Phoenix I Restoration and Construction, LLC

14032 Distribution Way

Farmers Branch, Texas 75234

 

Dale Sellers, President/Chief Executive officer

 

MAP

 