File #: 23-1065    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 4/11/2023 In control: Park & Recreation Department
On agenda: 5/10/2023 Final action:
Title: Authorize a construction services contract for the Cadillac Heights Park Demolition and Reestablishment Project located at 2924 Cedar Crest Boulevard - Texas Standard Construction Ltd., lowest responsible bidder of six - Not to exceed $748,177.40 - Financing: Park and Recreation Facilities Fund (2006 General Obligation Bond Fund)
Indexes: 4
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life, Arts & Culture

AGENDA DATE:                     May 10, 2023

COUNCIL DISTRICT(S):                     4

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     John D. Jenkins

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the Cadillac Heights Park Demolition and Reestablishment Project located at 2924 Cedar Crest Boulevard - Texas Standard Construction Ltd., lowest responsible bidder of six - Not to exceed $748,177.40 - Financing:  Park and Recreation Facilities Fund (2006 General Obligation Bond Fund) 

 

Body

BACKGROUND

 

March 10, 2023, six bids were received for the Cadillac Heights Park Demolition and Reestablishment project. The work includes demolition of street, sidewalks, driveways, and stormwater curb-inlets as well as regrading and installation of new sections of the underground stormwater drain system.

 

This action will authorize the award of a construction services contract with Texas Standard Construction Ltd., for the Cadillac Heights Park Demolition and Reestablishment Project located at 2924 Cedar Crest Boulevard for a total contract amount of $748,177.40.

 

The following chart illustrates Texas Standard Construction’s Ltd.’s contractual activities with the City of Dallas for the past three years:

                     

                     PBW                     DWU                     PKR       TRN

 

Projects Completed                     54                     3                     11                     0

Change Orders                     18                     3                     5                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

 

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                          December 2022

Design Completed                                          February 2023

Begin Construction                                           June 2023

Complete Construction                      September 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On April 20, 2023, the Park and Recreation Board will consider authorizing a construction services contract for the Cadillac Heights Park Demolition and Reestablishment Project located at 2924 Cedar Crest Boulevard.

 

FISCAL INFORMATION

 

Fund

FY 2023

FY 2024

Future Years

Park and Recreation Facilities Fund (2006 General Obligation Bond Fund)

$748,177.40

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$748,177.40

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

33.00%

33.00%

$246,898.54

This contract exceeds the M/WBE goal.

Texas Standard Construction Ltd. - Local; Workforce - 97.00% Local

 

PROCUREMENT INFORMATION

 

The following six bids were received and opened on March 10, 2023:

 

*Denotes successful bidder

 

Bidders                                                                      Total Bid                                                                Rank

                                          

*Texas Standard Construction Ltd.                     $   748,177.40                     1

 5511 W. Ledbetter Dr.

 Dallas, TX 75211

Greeniverse Construction, LLC                     $   832,176.99                     2

MECO Contractors, LLC                                          $   844,044.08                     3

J.B. & Co., LLC                                          $   987,950.00                     4

Cole Construction, Inc.                                          $1,191,037.94                     5

RNDI Companies, Inc.                                          $1,433,060.00                     6

 

OWNER

 

Texas Standard Construction Ltd.

 

Ronald H Dalton, President

 

MAP

 

Attached