STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: May 24, 2023
COUNCIL DISTRICT(S): 5
DEPARTMENT: Department of Transportation
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT
title
Authorize (1) the acceptance of a grant from the United States Department of Transportation Federal Highway Administration through the Texas Department of Transportation (TxDOT) for the Surface Transportation Block Grant Program (Agreement No. CSJ 0918-47-390, CFDA No. 20.205) as Federal share in the total project cost of $2,406,614.00, which includes $1,840,000.00 as Federal participation for environmental assessment, engineering, construction, and direct state costs, $106,614.00 as State participation for indirect state costs, and $460,000.00 as local participation for environmental assessment, engineering, construction, and direct state costs paid to TxDOT prior to construction for cost related to the preparation of preliminary engineering (schematic and environmental), final design, plans, specifications and estimates, and the reconstruction of Lake June Road from U.S. 175 to Gillette Street including rehabilitation of a 6 to 4 lane roadway including full depth pavement repair to include bike lanes, sidewalks, lighting, and traffic signal at Gillette Street and Lake June Road; (2) a local match in the amount of $460,000.00; (3) the disbursement of funds in the amount of $460,000.00 to TxDOT from the Coronavirus State and Local Fiscal Recovery Fund; and (4) execution of the Advance Funding Agreement with TxDOT and all terms, conditions, and documents required by the grant agreement - Total amount of $460,000.00 - Financing: Coronavirus State and Local Fiscal Recovery Fund
body
BACKGROUND
The Texas Transportation Commission passed Minute Order No. 116292 authorizing the State to undertake and complete a highway improvement or other transportation project generally described as rehabilitation of Lake June Road in the City of Dallas, which included this project.
The City of Dallas desires to enter into an Advanced Funding Agreement (AFA) with TxDOT to accept federal funding through the Surface Transportation Block Grant (STBG) Program for cost related to the preparation of preliminary engineering (schematic and environmental), final design, plans, specifications and estimates, and the reconstruction of Lake June Road from U.S. 175 to Gillette Street including rehabilitation of a 6 to 4 lane roadway including full depth pavement repair to include bike lanes, sidewalks, lighting, and traffic signal at Gillette Street and Lake June Road (“Project”).
TxDOT is the lead agency to administer the environmental assessment, engineering, and construction of the Project pursuant to the terms of the AFA, and the U.S. Department of Transportation will provide the State with funding for 80 percent of costs for environmental assessment, engineering, and construction activities and direct state costs as Federal participation.
The total estimated project cost is $2,406,614.00 which includes $1,840,000.00 as Federal participation for environmental assessment, engineering, construction, and direct state costs, $106,614.00 as State participation for indirect state costs, and 20 percent City of Dallas participation in the amount of $460,000.00 for environmental assessment, engineering, construction, and direct state costs paid to TxDOT prior to construction.
This action will authorize an AFA with TxDOT for environmental assessment, engineering, and construction of the Project and local participation in the amount of $460,000.00 to be disbursed to TxDOT.
Any change orders or cost overruns are the responsibility of the City of Dallas.
Coronavirus State and Local Fiscal Recovery Funds are eligible within the Qualified Census Tract areas to improve various intersections to promote the safety of all right-of-way users including motorist, cyclists, and pedestrians.
ESTIMATED SCHEDULE OF PROJECT
Began Design June 2022
Complete Design October 2023
Begin Construction June 2024
Complete Construction June 2026
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On June 23, 2021, the City Council authorized the acceptance of grant funds from the U.S. Department of Treasury for the Coronavirus State and Local Fiscal Recovery Fund to provide relief during the ongoing COVID-19 pandemic by Resolution No. 21-1149.
On September 28, 2022, the City Council authorized the final reading and adoption of the appropriation ordinance for the FY 2022-23 City of Dallas Operating, Capital, and Grant & Trust Budgets, which included the American Rescue Plan Act funds from the U.S. Department of Treasury for the Coronavirus State and Local Fiscal Recovery Fund by Resolution No. 22-1480.
FISCAL INFORMATION
Fund |
FY 2023 |
FY 2024 |
Future Years |
Coronavirus State and Local Fiscal Recovery Fund |
$60,000.00 |
$400,000.00 |
$0.00 |
Federal Participation (STBG) $1,840,000.00
Indirect State Participation $ 106,614.00
City of Dallas Participation $ 460,000.00
Total Project Cost $2,406,614.00
MAP
Attached