Title: Authorize a construction services contract for the construction of Street Reconstruction Group 17-5001 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of four - Not to exceed $10,153,024.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($7,287,224.00), Water Construction Fund ($1,380,150.00), Wastewater Capital Improvement F Fund ($1,469,150.00), and Wastewater Construction Fund ($16,500.00)
Indexes: 5
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: September 27, 2023
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the construction of Street Reconstruction Group 17-5001 (list attached to the Agenda Information Sheet) - Estrada Concrete Company, LLC, lowest responsible bidder of four - Not to exceed $10,153,024.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($7,287,224.00), Water Construction Fund ($1,380,150.00), Wastewater Capital Improvement F Fund ($1,469,150.00), and Wastewater Construction Fund ($16,500.00)

Body
BACKGROUND

This action will authorize a construction services contract with Estrada Concrete Company, LLC for the construction of two street reconstruction projects as Street Reconstruction Group 17-5001.

The project group scope will provide replacement of the existing deteriorating street asphalt pavement with reinforced concrete pavement, curb, gutter, sidewalk, driveway and alley approaches, paving marking, possible replacement of the drainage system, and water and wastewater improvements.

Following are the locations and construction cost for each project:

Project Council District Amount
Rosemont Road from |99|$2,533,714.00
South Buckner Boulevard
to Hillburn Drive

Rosemont Road from|99|$7,619,310.00
Hillburn Drive to
North Jim Miller Road

Estrada Concrete Company, LLC is a Hutchins-based corporation and is a registered vendor with the City of Dallas.

The following chart illustrates Estrada Concrete Company, LLC's contractual activities with the City of Dallas for the past three years.

PBW DWU PKR TRN

Projects Completed|999910|Active Projects 17|99910|Change Orders|999910|Projects Requiring Liquidated Damages|999910|Projects Completed by Bonding Company|999910|