Title: Authorize (1) a Construction Manager at Risk Agreement, with JE Dunn-Russell, a joint venture, best value proposer of two, for pre-construction and construction services for the Cotton Bowl Renovation, Rehabilitation and Addition Project (or "Project"), located at 3750 The Midway, for (1) preconstruction services for the Cotton Bowl Project for a fee in the amount of $145,000.00; and (2) construction management services at a rate of two and ninety-five hundredths percent (2.95%) of the cost of work included as part of the guaranteed maximum price within the total project construction budget of $110,000,000.00; (32) the establishment of appropriations in an amount not to exceed $32,145,000.00 in the Fair Park Revenue Bonds, Series 2023 Fund Facilities Venue Project Fund; and (4) commencement of material and equipment acquisition for a portion of the anticipated work under Part One of the Project, as long as it does not exceed the appropriated amount of $32,000,000.00 - JE Dunn-Russell, ...
Indexes: 7
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life, Arts & Culture
AGENDA DATE: December 13, 2023
COUNCIL DISTRICT(S):|910|DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT

Title
Authorize (1) a Construction Manager at Risk Agreement, with JE Dunn-Russell, a joint venture, best value proposer of two, for pre-construction and construction services for the Cotton Bowl Renovation, Rehabilitation and Addition Project (or "Project"), located at 3750 The Midway, for (1) preconstruction services for the Cotton Bowl Project for a fee in the amount of $145,000.00; and (2) construction management services at a rate of two and ninety-five hundredths percent (2.95%) of the cost of work included as part of the guaranteed maximum price within the total project construction budget of $110,000,000.00; (32) the establishment of appropriations in an amount not to exceed $32,145,000.00 in the Fair Park Revenue Bonds, Series 2023 Fund Facilities Venue Project Fund; and (4) commencement of material and equipment acquisition for a portion of the anticipated work under Part One of the Project, as long as it does not exceed the appropriated amount of $32,000,000.00 - JE Dunn-Russell, a joint venture, best value proposer of two - Not to exceed $145,000.00 - Financing: Fair Park Revenue Bonds, Series 2023 Bond Facilities Venue Project Fund

Body
BACKGROUND

This Construction Manager at Risk Agreement will include pre-construction and construction services for the Project that includes improvements to mechanical, electrical and plumbing systems, concessions areas, restrooms and vertical transportation systems as well as an expansion to the west side concourses.

The Project has a total estimated construction budget of $110,000,000.00 and will be constructed over two timeframes with Phase One, with an estimated construction budget of $56,000,000.00 (of which $32,000145,000.00 is appropriated with this actio...